Himachal fails to develop biotechnology park in 12 years: CAG

Image
IANS Shimla
Last Updated : Apr 04 2017 | 3:13 PM IST

Himachal Pradesh has failed to develop a biotechnology park in Solan district with the Centre's assistance in 12 years despite incurring an unfruitful expenditure of Rs 2.07 crore and axing 897 trees, the Comptroller and Auditor General of India (CAG) has said.

The park, yet to be established, was initially proposed to be commissioned by 2006-07.

The central government had accorded approval for setting up the biotechnology park in March 2005 at a cost of Rs 38.66 crore under public-private-partnership (PPP) mode, said the CAG report tabled in the assembly last week.

The central government proposed to invest Rs 9 crore in the park, while the state committed to invest Rs 7.55 crore. The remaining amount was to be pooled in by the investor.

The project was to be implemented by 2006-07 and no funding from the central government was to be released for the project beyond March 2007, the report said.

The Centre had released Rs 50 lakh as token grant in March 2005 and the state government released Rs 2.21 crore during 2004-08.

However, the state department of industries could not involve any private partner for the proposed park that would have a biotechnology incubation centre and a biotechnology industrial cluster.

Initially, the biotechnology park was to be set up at Kotla Barog in Solan district but no investor came up for development of the project.

In February 2008, the project site was changed to Aduwal on the Nalagarh-Swarghat national highway.

According to the CAG, the department had released Rs 45.73 lakh in 2009 to a consultant for preparation of a feasibility report, business plan and selection of promoter for setting up the park at Kotla Barog.

However, the change of the project site resulted in an unfruitful expenditure of 45.73 lakh.

Later, the department in 2009 entered into an agreement with a firm -- at an estimated cost of Rs 43.93 lakh -- for preparation of feasibility report, business plan and selection of promoter for the park at Aduwal.

It paid Rs 22.12 lakh for the feasibility report. However, the firm could also not select any promoter for the project and, ultimately, the work relating to establishment of the park was transferred to the industries department.

Till October last year, the industries department was in the process of transfer of environment clearance and land in its name.

The CAG slammed the government for faulty planning in establishing the park that resulted in expenditure of Rs 2.07 crore.

Besides, the biodiversity of forest land diverted for the park had been changed by cutting 897 green trees, resulting in degradation of environment in the heavily industrialised area.

--IANS

vg/sm/dg

Disclaimer: No Business Standard Journalist was involved in creation of this content

*Subscribe to Business Standard digital and get complimentary access to The New York Times

Smart Quarterly

₹900

3 Months

₹300/Month

SAVE 25%

Smart Essential

₹2,700

1 Year

₹225/Month

SAVE 46%
*Complimentary New York Times access for the 2nd year will be given after 12 months

Super Saver

₹3,900

2 Years

₹162/Month

Subscribe

Renews automatically, cancel anytime

Here’s what’s included in our digital subscription plans

Exclusive premium stories online

  • Over 30 premium stories daily, handpicked by our editors

Complimentary Access to The New York Times

  • News, Games, Cooking, Audio, Wirecutter & The Athletic

Business Standard Epaper

  • Digital replica of our daily newspaper — with options to read, save, and share

Curated Newsletters

  • Insights on markets, finance, politics, tech, and more delivered to your inbox

Market Analysis & Investment Insights

  • In-depth market analysis & insights with access to The Smart Investor

Archives

  • Repository of articles and publications dating back to 1997

Ad-free Reading

  • Uninterrupted reading experience with no advertisements

Seamless Access Across All Devices

  • Access Business Standard across devices — mobile, tablet, or PC, via web or app

More From This Section

First Published: Apr 04 2017 | 3:04 PM IST

Next Story