Acquire land after sanction of works to avoid project delay: Rly panel

Image
Press Trust of India New Delhi
Last Updated : Mar 11 2018 | 11:50 AM IST
A railway panel has suggested that land for the national transporter's projects should be acquired only after sanction of works or before signing of construction contracts, to avoid delays in their completion.
According to a report of the statistics ministry submitted last month, more than three-fifths of the total 349 delayed central projects belong to the railways, causing a cost overrun of Rs 1.73 lakh crore.
"Delay in land acquisition and shifting of utilities are causing abnormal delay in commencing and completing the project. These two activities should be taken up and completed before finalising the contracts for actual execution of the work," the report said.
"These two should be taken up immediately after sanction of projects."
Under the present practice, construction contracts are processed without finalising drawing and plans, land acquisition and shifting of utilities like removal of trees, electrical poles etc., the report said.
The panel in its report on 'Improving Project Execution and Monitoring' has said while the completion periods are given as three to four years in the contract, in many cases it takes double the duration.
This, the panel said was adversely affecting the profit of contractors "leading to termination of many contracts and also arbitrations and litigations."
The report has said that General Managers should be delegated the powers for sanctioning part estimates and incurring expenditure for land acquisition and shifting of utilities to expedite the process.
The cost of the delay in railway projects can be estimated by the data provided in the statistics ministry report which monitored 350 projects of Indian Railways in October last year.
The total anticipated cost of the 213 delayed projects ballooned to Rs 2,96,496.70 crore from original cost of Rs 1,23,103.45 crore because of delays, it said, which is an overall cost escalation of 140.85 per cent.
The report of the rail panel was submitted to the Railway Board last month and is under consideration.

Disclaimer: No Business Standard Journalist was involved in creation of this content

*Subscribe to Business Standard digital and get complimentary access to The New York Times

Smart Quarterly

₹900

3 Months

₹300/Month

SAVE 25%

Smart Essential

₹2,700

1 Year

₹225/Month

SAVE 46%
*Complimentary New York Times access for the 2nd year will be given after 12 months

Super Saver

₹3,900

2 Years

₹162/Month

Subscribe

Renews automatically, cancel anytime

Here’s what’s included in our digital subscription plans

Exclusive premium stories online

  • Over 30 premium stories daily, handpicked by our editors

Complimentary Access to The New York Times

  • News, Games, Cooking, Audio, Wirecutter & The Athletic

Business Standard Epaper

  • Digital replica of our daily newspaper — with options to read, save, and share

Curated Newsletters

  • Insights on markets, finance, politics, tech, and more delivered to your inbox

Market Analysis & Investment Insights

  • In-depth market analysis & insights with access to The Smart Investor

Archives

  • Repository of articles and publications dating back to 1997

Ad-free Reading

  • Uninterrupted reading experience with no advertisements

Seamless Access Across All Devices

  • Access Business Standard across devices — mobile, tablet, or PC, via web or app

More From This Section

First Published: Mar 11 2018 | 11:50 AM IST

Next Story