'Airport projects hit by lack of national policy, land issues'

Image
Press Trust of India Mumbai
Last Updated : Mar 27 2014 | 7:52 PM IST
Only a half of the ongoing airport projects in the country would be completed in the next three years while the rest would be delayed owing to the tough land acquisition norms, regulatory hurdles and absence of a national-level policy, a ratings agency said in a report.
"Currently, about 64 airport projects worth investment of about Rs 1,51,500 crore are under implementation/announced stage. Of these, about 33 projects accounting for about 25 per cent of the total outstanding investment are under advance stage of construction and are expected to get completed up to FY17," Care Research said.
Noting that the Planning Commission has envisaged investment of about Rs 87,700 crore during the 12th Five Year Plan in the sector to meet the increasing demand, the report said that unlike other infrastructure projects, the airport project requires substantial land at a single location.
CARE Research expects the air passenger traffic to witness a double digit growth during FY14-17 but a moderate growth in air passenger handling capacity would dampen air passenger traffic growth up to FY17, it said.
"Setting up of an airport needs approval from about 16-17 agencies at Central and state levels. Therefore airport projects are prone to time overruns," it said.
Stating that delay in land acquisitions is expected to remain a major challenge, the report said balance projects involving 75 per cent of outstanding investment are expected to commission beyond FY'17.
The report also observed that airport projects have witnessed inordinate delays in the past, primarily on account of land acquisition issues, procedural delays, viability issues and non-availability of funds for expansion.
The airport infrastructure segment in the country does not have a long-term national level policy, though construction of airports takes at least about three years for completion, it said.
Muted central assistance and non-viability of some projects are likely to impact development of airport infrastructure and high leverage of airport infrastructure companies may act as a deterrent for private participation in the near term, the report added.
*Subscribe to Business Standard digital and get complimentary access to The New York Times

Smart Quarterly

₹900

3 Months

₹300/Month

SAVE 25%

Smart Essential

₹2,700

1 Year

₹225/Month

SAVE 46%
*Complimentary New York Times access for the 2nd year will be given after 12 months

Super Saver

₹3,900

2 Years

₹162/Month

Subscribe

Renews automatically, cancel anytime

Here’s what’s included in our digital subscription plans

Exclusive premium stories online

  • Over 30 premium stories daily, handpicked by our editors

Complimentary Access to The New York Times

  • News, Games, Cooking, Audio, Wirecutter & The Athletic

Business Standard Epaper

  • Digital replica of our daily newspaper — with options to read, save, and share

Curated Newsletters

  • Insights on markets, finance, politics, tech, and more delivered to your inbox

Market Analysis & Investment Insights

  • In-depth market analysis & insights with access to The Smart Investor

Archives

  • Repository of articles and publications dating back to 1997

Ad-free Reading

  • Uninterrupted reading experience with no advertisements

Seamless Access Across All Devices

  • Access Business Standard across devices — mobile, tablet, or PC, via web or app

More From This Section

First Published: Mar 27 2014 | 7:52 PM IST

Next Story