The construction of the much-awaited Signature Bridge on the Yamuna will pick up pace as the CPWD has endorsed an additional estimate of around Rs 231 crore of the DTTDC to complete the project, an official has said.
The PWD had sought the Central Public Works Department's "expert opinion" after the Delhi Tourism and Transportation Development Corporation (DTTDC) had submitted a revised estimate of Rs 1,575 crore.
Of the revised estimate, the Delhi government has released Rs 1,344 crore for the project that has witnessed cost escalation several times since its construction started.
The official, who is privy to information related to the project, said out of the Rs 231 crore, the Delhi government's Public Works Department (PWD) has already given Rs 36 crore to the DTTDC, but it had not released the amount to the contractor in view of the PWD seeking the CPWD's "expert opinion".
Last week, the Delhi High Court pulled up the PWD and the DTTDC for "quibbling over" the amount to be paid for construction of the "long overdue" Signature Bridge.
The court also gave them the last opportunity to ensure the project is completed without any increase in cost.
The bridge, once completed, will share the burden of vehicular traffic, currently being borne by the Wazirabad bridge, used to commute to and from Delhi and Ghaziabad.
The bridge will connect the Outer Ring Road on the western bank with the Wazirabad Road on the eastern side of the Yamuna.
"The PWD had objected to the revised estimate of Rs 1,575 crore as submitted by the DTTDC to complete the construction work of Signature Bridge.
"Thereafter, the PWD sought the expert opinion of the CPWD, which has now endorsed the revised estimate of the DTTDC to complete the project," a senior official said.
He said the issue of revised estimate of the bridge will be sent to the Expenditure Finance Committee (EFC) of the Delhi government and then, the cabinet, chaired by Chief Minister Arvind Kejriwal, will take a final decision on it.
Announced in 2004, the project received a nod from the Delhi cabinet in 2007 and it was initially expected to be completed at a modified estimate of Rs 1,131 crore before the Commonwealth Games, which were held here in October, 2010.
The bridge had obtained environmental clearance in 2011 and was set to be completed by December 2013.
The date of completing project was pushed to June 2016 and then to July 2017, which was further pushed to December 2017.
Disclaimer: No Business Standard Journalist was involved in creation of this content
You’ve reached your limit of {{free_limit}} free articles this month.
Subscribe now for unlimited access.
Already subscribed? Log in
Subscribe to read the full story →
Smart Quarterly
₹900
3 Months
₹300/Month
Smart Essential
₹2,700
1 Year
₹225/Month
Super Saver
₹3,900
2 Years
₹162/Month
Renews automatically, cancel anytime
Here’s what’s included in our digital subscription plans
Exclusive premium stories online
Over 30 premium stories daily, handpicked by our editors


Complimentary Access to The New York Times
News, Games, Cooking, Audio, Wirecutter & The Athletic
Business Standard Epaper
Digital replica of our daily newspaper — with options to read, save, and share


Curated Newsletters
Insights on markets, finance, politics, tech, and more delivered to your inbox
Market Analysis & Investment Insights
In-depth market analysis & insights with access to The Smart Investor


Archives
Repository of articles and publications dating back to 1997
Ad-free Reading
Uninterrupted reading experience with no advertisements


Seamless Access Across All Devices
Access Business Standard across devices — mobile, tablet, or PC, via web or app