"TLDP-III (4 X 33) 132 MW Power Station in West Bengal has been completely restored on January 18, 2017 which was under complete shutdown for restoration work of GIS (Line-I Bay)," NHPC Ltd said in a BSE filing today.
Earlier on Monday, the company had said, "TLDP-III (4X33) 132 MW power station in West Bengal shall be under complete shutdown from January 16 to January 23, 2017 for restoration work of GIS (Line-I Bay).
The power station is designed to generate 594.07 million units annually in 90 per cent dependable year. The units I, II,III and IV were commissioned on January 28, January 16, February 24 and March 31, respectively in 2013.