The scheduled date to complete the 56 km Agra to Firozabad section on the highway was January 28, 2018, PNC Infratech Managing Director Yogesh Jain said.
"We completed the project on October 31, 2017, 89 days ahead of the scheduled date," he said.
The amount of Rs 58.23 crore has been paid by the Uttar Pradesh Expressways Industrial Development Authority (UPEIDA), UP government, Jain said.
The large team of experts, new age machinery and building material purchased in advance helped in early completion, Jain added.
Its revenues from operations also rose to Rs 472.48 crore, from Rs 463.64 crore, during the corresponding three-month period of the previous fiscal.
Agra-based PNC Infratech has presence in over 12 states in India.
Disclaimer: No Business Standard Journalist was involved in creation of this content
You’ve reached your limit of {{free_limit}} free articles this month.
Subscribe now for unlimited access.
Already subscribed? Log in
Subscribe to read the full story →
Smart Quarterly
₹900
3 Months
₹300/Month
Smart Essential
₹2,700
1 Year
₹225/Month
Super Saver
₹3,900
2 Years
₹162/Month
Renews automatically, cancel anytime
Here’s what’s included in our digital subscription plans
Exclusive premium stories online
Over 30 premium stories daily, handpicked by our editors


Complimentary Access to The New York Times
News, Games, Cooking, Audio, Wirecutter & The Athletic
Business Standard Epaper
Digital replica of our daily newspaper — with options to read, save, and share


Curated Newsletters
Insights on markets, finance, politics, tech, and more delivered to your inbox
Market Analysis & Investment Insights
In-depth market analysis & insights with access to The Smart Investor


Archives
Repository of articles and publications dating back to 1997
Ad-free Reading
Uninterrupted reading experience with no advertisements


Seamless Access Across All Devices
Access Business Standard across devices — mobile, tablet, or PC, via web or app