6 out of 10 projects in Mumbai revise delivery targets after RERA: Report

Deadline for nearly 25% of the registered units extended by up to 18 months

real estate
Data show revenue collected from stamp duty and registration fees had actually begun to slow down in the months prior to demonetisation
Raghavendra Kamath Mumbai
Last Updated : Aug 24 2017 | 1:33 AM IST

Six out of ten under-construction projects in Mumbai have revised their delivery targets by more than a year after Real Estate Regulation and Development (RERA) Act, 2016 into force, said a new report.

About 57 per cent of projects registered with RERA authority in Maharashtra have extended the delivery timelines, said a survey by property consultant Knight Frank. The report covered residential units registered with the Maharashtra RERA regulator or the MahaRERA in the Mumbai suburbs until August 16, 2017.

For nearly one-fourth (24 per cent) of the 1, 07,875 registered units the completion deadline was pushed by 12 to 18 months. The report further found that 19 per cent under-construction homes were delayed by 24 to 48 months and 10 per cent of these properties would not get completed before four years.

Just about one-third of the units listed with the MahaRERA are set to be completed on time, the report added.

Samantak Das, Chief Economist and National Director-Research, Knight Frank India, said: "Our analysis of the database shows that a significant number of residential units lie unsold in projects that should have been completed as per the initial commitment of delivery. Another crucial trend that comes to light is the lack of seriousness in meeting time commitments agreed upon by the buyers before RERA came to effect.

Going forward, the MahaRERA database or similar information networks created by other states would bring the missing information parity between buyers and developers. Availability of such detailed information would also play a crucial role in the financial planning of home buyers setting a new paradigm in the real estate sector."

Projects registered until August 16 in key central and western suburbs were covered in the analysis. This included the Andheri and Borivali Talukas that stretch from Bandra in the south and extend up to Dahisar in the north. In the central suburbs, the study covered the Kurla Taluka, spanning between Tilak Nagar and Mulund.

The study also found that at least 48 per cent of the registered units stood unsold. Nearly a third of the units in projects that should have been complete as per their initial proposed date of completion, still lie unsold.

The unsold inventory level for units is scheduled to be delivered by July 2018, as per the initial commitment of completion that stands at a staggering 55 per cent.

Out of 16,000 projects under construction in Maharashtra, about 10,000 have filed for registrations.

One subscription. Two world-class reads.

Already subscribed? Log in

Subscribe to read the full story →
*Subscribe to Business Standard digital and get complimentary access to The New York Times

Smart Quarterly

₹900

3 Months

₹300/Month

SAVE 25%

Smart Essential

₹2,700

1 Year

₹225/Month

SAVE 46%
*Complimentary New York Times access for the 2nd year will be given after 12 months

Super Saver

₹3,900

2 Years

₹162/Month

Subscribe

Renews automatically, cancel anytime

Here’s what’s included in our digital subscription plans

Exclusive premium stories online

  • Over 30 premium stories daily, handpicked by our editors

Complimentary Access to The New York Times

  • News, Games, Cooking, Audio, Wirecutter & The Athletic

Business Standard Epaper

  • Digital replica of our daily newspaper — with options to read, save, and share

Curated Newsletters

  • Insights on markets, finance, politics, tech, and more delivered to your inbox

Market Analysis & Investment Insights

  • In-depth market analysis & insights with access to The Smart Investor

Archives

  • Repository of articles and publications dating back to 1997

Ad-free Reading

  • Uninterrupted reading experience with no advertisements

Seamless Access Across All Devices

  • Access Business Standard across devices — mobile, tablet, or PC, via web or app

Next Story