HC pulls up RIL for starting project without green nod

Image
Press Trust of India Chennai
Last Updated : Jan 20 2013 | 1:04 AM IST

The Madras High Court has taken exception to Reliance Industries (RIL) going ahead with a gas pipeline related project in the union territory of Puducherry without obtaining environmental clearance in advance.

Passing an order on a PIL filed by S Sai Kumar, hailing from Yanam, a territory of Puducherry, a Division Bench comprising Justices Prabha Sridevan and G M Akbar Ali said yesterday that the fact that Reliance had obtained approval after commencing the project was not enough.

The court also asked the Puducherry government to ask for and obtain an environment impact report from experts, since the project area spread over mangrove forests.

The Bench said it was disturbed by the company's attitude and expected it to have greater social responsibility. "If an environment disaster strikes, it will strike the mighty and the weak equally. We do not understand why the company should have commenced production and then obtained approval," the bench said.

In his petition, Kumar asked the court to restrain the respondents from establishing a 'block valve station' for the pipeline project in Dariyalatippa village without due process of law as laid down in the Madras River Conservancy Act. He said he apprehended there would be environmental damage if the project was established.

The Puducherry government and the company had entered into an MoU for implementing a national gas development project. 25 per cent of the local population were fishermen dependent on the river. If the project was not halted, then, by virtue of destruction of coconut plantation and mangrove forests, the possibility of flooding would increase, the petitioner said.

The mangrove forests should be protected, Kumar said in his petition.

Disposing of the petition, the bench said the applicant should come forward with an environmental management plan, which must be cleared by experts. To prevent possible future damage, the government should also be satisfied that the damage was not irreversible.

The applicant should be prepared and must sufficiently secure the cost of reversing any damage, the bench said.

The government should also have in place necessary infrastructure to maintain periodical survey and enforce stipulations subject to which the permission may be granted.

Before granting approval, the government should call upon the company to publish its proposal so that the public, particularly those who were likely to be affected, were made aware of the proposed action.

This would ensure transparency in the process and at least safeguard against a possible misjudgement if a mishap occurs, the bench said.

*Subscribe to Business Standard digital and get complimentary access to The New York Times

Smart Quarterly

₹900

3 Months

₹300/Month

SAVE 25%

Smart Essential

₹2,700

1 Year

₹225/Month

SAVE 46%
*Complimentary New York Times access for the 2nd year will be given after 12 months

Super Saver

₹3,900

2 Years

₹162/Month

Subscribe

Renews automatically, cancel anytime

Here’s what’s included in our digital subscription plans

Exclusive premium stories online

  • Over 30 premium stories daily, handpicked by our editors

Complimentary Access to The New York Times

  • News, Games, Cooking, Audio, Wirecutter & The Athletic

Business Standard Epaper

  • Digital replica of our daily newspaper — with options to read, save, and share

Curated Newsletters

  • Insights on markets, finance, politics, tech, and more delivered to your inbox

Market Analysis & Investment Insights

  • In-depth market analysis & insights with access to The Smart Investor

Archives

  • Repository of articles and publications dating back to 1997

Ad-free Reading

  • Uninterrupted reading experience with no advertisements

Seamless Access Across All Devices

  • Access Business Standard across devices — mobile, tablet, or PC, via web or app

More From This Section

First Published: Jul 21 2010 | 2:00 PM IST

Next Story