The Madras High Court has taken exception to Reliance Industries (RIL) going ahead with a gas pipeline related project in the union territory of Puducherry without obtaining environmental clearance in advance.
Passing an order on a PIL filed by S Sai Kumar, hailing from Yanam, a territory of Puducherry, a Division Bench comprising Justices Prabha Sridevan and G M Akbar Ali said yesterday that the fact that Reliance had obtained approval after commencing the project was not enough.
The court also asked the Puducherry government to ask for and obtain an environment impact report from experts, since the project area spread over mangrove forests.
The Bench said it was disturbed by the company's attitude and expected it to have greater social responsibility. "If an environment disaster strikes, it will strike the mighty and the weak equally. We do not understand why the company should have commenced production and then obtained approval," the bench said.
In his petition, Kumar asked the court to restrain the respondents from establishing a 'block valve station' for the pipeline project in Dariyalatippa village without due process of law as laid down in the Madras River Conservancy Act. He said he apprehended there would be environmental damage if the project was established.
The Puducherry government and the company had entered into an MoU for implementing a national gas development project. 25 per cent of the local population were fishermen dependent on the river. If the project was not halted, then, by virtue of destruction of coconut plantation and mangrove forests, the possibility of flooding would increase, the petitioner said.
The mangrove forests should be protected, Kumar said in his petition.
Disposing of the petition, the bench said the applicant should come forward with an environmental management plan, which must be cleared by experts. To prevent possible future damage, the government should also be satisfied that the damage was not irreversible.
The applicant should be prepared and must sufficiently secure the cost of reversing any damage, the bench said.
The government should also have in place necessary infrastructure to maintain periodical survey and enforce stipulations subject to which the permission may be granted.
Before granting approval, the government should call upon the company to publish its proposal so that the public, particularly those who were likely to be affected, were made aware of the proposed action.
This would ensure transparency in the process and at least safeguard against a possible misjudgement if a mishap occurs, the bench said.
You’ve reached your limit of {{free_limit}} free articles this month.
Subscribe now for unlimited access.
Already subscribed? Log in
Subscribe to read the full story →
Smart Quarterly
₹900
3 Months
₹300/Month
Smart Essential
₹2,700
1 Year
₹225/Month
Super Saver
₹3,900
2 Years
₹162/Month
Renews automatically, cancel anytime
Here’s what’s included in our digital subscription plans
Exclusive premium stories online
Over 30 premium stories daily, handpicked by our editors


Complimentary Access to The New York Times
News, Games, Cooking, Audio, Wirecutter & The Athletic
Business Standard Epaper
Digital replica of our daily newspaper — with options to read, save, and share


Curated Newsletters
Insights on markets, finance, politics, tech, and more delivered to your inbox
Market Analysis & Investment Insights
In-depth market analysis & insights with access to The Smart Investor


Archives
Repository of articles and publications dating back to 1997
Ad-free Reading
Uninterrupted reading experience with no advertisements


Seamless Access Across All Devices
Access Business Standard across devices — mobile, tablet, or PC, via web or app