In a major setback to Ajit Gulabchand’s ambitious hill city project, the Union environment ministry today asked the Maharashtra government to initiate action against Lavasa Corporation for violation of green norms. The notice came within hours of Gulabchand’s statement that an environment ministry committee has recommended conditional clearances for the first phase of the project.
Gulabchand, chairman of Hindustan Construction Company (HCC), was talking to the media on the sidelines of the annual general meeting of his company this morning. By evening, the ministry stressed that part of the construction had been undertaken at the project site in Pune without obtaining a green nod.
The hill station township is being constructed by Lavasa Corporation, a subsidiary of HCC. The company has invested Rs 3,000 crore so far. But Lavasa has been caught up in the regulatory net for several months now.
The company has incurred losses of about Rs 300 crore so far due to the stop-work notice issued by environment minister Jairam Ramesh. The stop -work notice came late last year. The ministry is preparing to give its view on the phase-I of the controversial project on June 15, when the matter comes up in the Bombay High Court for hearing. On the fate of the project, Ramesh said whatever his ministry has to say will be presented in the court.
The Maharashtra government was quick to react to the Ministry of Environment and Forests' (MoEF) directive. A senior state government official told Business Standard that “according to the MoEF directive, a case will be filed before the chief judicial magistrate against Lavasa Corporation under the Environment Protection Act, 1986”.
In a letter to the government, the MoEF said the state should take necessary action against the Lavasa project.
The ministry said during an appraisal of request for green clearance for the development of the 2,000-hectare Hill Station Township "it was found that constructions/developments in a 681 hectare area was in progress without obtaining prior environmental clearance".
Noting that it had issued showcause notices on November 25 last year and final directions on January 17 this year, the ministry said the constructions and developments in the 681- hectare are violations of the 1986 Act. As many as 257 residential units on 681.3 hectares were under construction when Ramesh imposed a stop-work order.
You’ve reached your limit of {{free_limit}} free articles this month.
Subscribe now for unlimited access.
Already subscribed? Log in
Subscribe to read the full story →
Smart Quarterly
₹900
3 Months
₹300/Month
Smart Essential
₹2,700
1 Year
₹225/Month
Super Saver
₹3,900
2 Years
₹162/Month
Renews automatically, cancel anytime
Here’s what’s included in our digital subscription plans
Exclusive premium stories online
Over 30 premium stories daily, handpicked by our editors


Complimentary Access to The New York Times
News, Games, Cooking, Audio, Wirecutter & The Athletic
Business Standard Epaper
Digital replica of our daily newspaper — with options to read, save, and share


Curated Newsletters
Insights on markets, finance, politics, tech, and more delivered to your inbox
Market Analysis & Investment Insights
In-depth market analysis & insights with access to The Smart Investor


Archives
Repository of articles and publications dating back to 1997
Ad-free Reading
Uninterrupted reading experience with no advertisements


Seamless Access Across All Devices
Access Business Standard across devices — mobile, tablet, or PC, via web or app