NLC's Tuticorin project to go on stream in Oct

Image
T E Narasimhan Chennai
Last Updated : Jan 25 2013 | 4:04 AM IST

The much-awaited Neyveli Lignite Corporation (NLC's) phase I of TPS (thermal power station) expansion at Tuticorin is set to be commissioned in October.

Delay in execution by Bharat Heavy Electricals Limited (Bhel) had resulted in cost and time overruns thereby hampering the 2x250-Mw project B Surender Mohan, who took over as chairman and managing director of NLC recently, said, "he (CMD of Bhel) and his team visited us recently and we had a fruitful discussion on the ongoing projects. Our aim should be not only to achieve the production targets but also to achieve the commissioning of projects under implementation.”

He said Bhel had ensured that the first unit of TPS-II expansion would be commissioned by October 2012 and the synchronisation of unit-II by November, 2012.

Earlier, NLC's former CMD AR Ansari had said, “we could have easily added 1,500 Mw of power to the grid, but we could not, because of them (Bhel). They (Bhel) are really a concern. Delay (in commissioning a power plant) ranges from 45 to 50 months.”

The TPS-II expansion unit would augment the power generation of NLC by another 500 Mw, enhancing the capacity to 3,240 Mw, said Mohan. NLC is the one major sources for Tamil Nadu.

The project — NLC Tamil Nadu Power Ltd (NTPL) — a joint venture between NLC and the Tamil Nadu Electricity Board (TNEB), at Tuticorin was sanctioned with the commissioning schedule of March 2012 and August 2012.

“Due to delay in execution by the package contractors, about 20 months delay is anticipated. Present physical progress is 61 per cent and commissioning is expected by December 2013 & March 2014,” said Mohan.

The Centre has sanctioned another 2x500 Mw Neyveli New Thermal Power project, as a replacement to the existing TPS-I (600 Mw) and this is scheduled to be commissioned in June 2015.

“Initial project activities have already commenced and tendering for major equipment and plants is in progress,” said Mohan.

Meanwhile, the Kundankulam nuclear power plant too is expected to be commissioned in the next few days. Both the development comes at a time when Tamil Nadu is facing a shortage of around 3,500 Mw.

*Subscribe to Business Standard digital and get complimentary access to The New York Times

Smart Quarterly

₹900

3 Months

₹300/Month

SAVE 25%

Smart Essential

₹2,700

1 Year

₹225/Month

SAVE 46%
*Complimentary New York Times access for the 2nd year will be given after 12 months

Super Saver

₹3,900

2 Years

₹162/Month

Subscribe

Renews automatically, cancel anytime

Here’s what’s included in our digital subscription plans

Exclusive premium stories online

  • Over 30 premium stories daily, handpicked by our editors

Complimentary Access to The New York Times

  • News, Games, Cooking, Audio, Wirecutter & The Athletic

Business Standard Epaper

  • Digital replica of our daily newspaper — with options to read, save, and share

Curated Newsletters

  • Insights on markets, finance, politics, tech, and more delivered to your inbox

Market Analysis & Investment Insights

  • In-depth market analysis & insights with access to The Smart Investor

Archives

  • Repository of articles and publications dating back to 1997

Ad-free Reading

  • Uninterrupted reading experience with no advertisements

Seamless Access Across All Devices

  • Access Business Standard across devices — mobile, tablet, or PC, via web or app

More From This Section

First Published: Aug 21 2012 | 12:31 AM IST

Next Story