NMDC mulls shifting proposed pellet plant site in Chhattisgarh

Company is considering changing the location of the pellet plant due to delay in land acquisition

Press Trust of India New Delhi
Last Updated : Apr 27 2014 | 12:36 PM IST
State-run iron ore miner NMDC is actively considering changing the location of its proposed two million tonne per annum (mtpa) pellet plant at Nagarnar in Chhattisgarh due to delay in land acquisition.

"As land acquisition is getting delayed due to delay in conducting gram sabha by the Chhattisgarh state government, a proposal for change in location of the pellet plant has been under active consideration," a company source said.

NMDC was mulling setting up a pellet plant adjacent to its upcoming greenfield steel facility at Nagarnar, which is likely to start production by next fiscal, at an estimated cost of Rs 800 crore.

The company in October last year had submitted the requisite application for obtaining environmental clearance. The terms of reference (TOR) was held in December.

The purpose of TOR, as per Ministry of Environment and Forest (MoEF), is to enable the project proponent for planning and designing environmental impact assessment (EIA).

"One of the points in the TOR minutes was that the EIA report should be submitted after the land acquisition," the source said, adding since land acquisition was getting delayed, there was no point in pursuing for environmental clearance.

"At this juncture, we do not have any other viable option left but shifting the location. We are considering that option actively," he said.

A decision on change of site would be taken after consulting with the competent authority, he added.

The change in location of the pellet plant would mean the transportation cost of the end-product to its steel plant would go up resulting some additional expenditure for the company when the steel plant stats production.

NMDC is setting up a three million tonnes per annum steel plant at Nagarnar in Bastar district with an investment of Rs 15,525 crore. The company has already received all statutory clearances for the project.
*Subscribe to Business Standard digital and get complimentary access to The New York Times

Smart Quarterly

₹900

3 Months

₹300/Month

SAVE 25%

Smart Essential

₹2,700

1 Year

₹225/Month

SAVE 46%
*Complimentary New York Times access for the 2nd year will be given after 12 months

Super Saver

₹3,900

2 Years

₹162/Month

Subscribe

Renews automatically, cancel anytime

Here’s what’s included in our digital subscription plans

Exclusive premium stories online

  • Over 30 premium stories daily, handpicked by our editors

Complimentary Access to The New York Times

  • News, Games, Cooking, Audio, Wirecutter & The Athletic

Business Standard Epaper

  • Digital replica of our daily newspaper — with options to read, save, and share

Curated Newsletters

  • Insights on markets, finance, politics, tech, and more delivered to your inbox

Market Analysis & Investment Insights

  • In-depth market analysis & insights with access to The Smart Investor

Archives

  • Repository of articles and publications dating back to 1997

Ad-free Reading

  • Uninterrupted reading experience with no advertisements

Seamless Access Across All Devices

  • Access Business Standard across devices — mobile, tablet, or PC, via web or app

More From This Section

First Published: Apr 27 2014 | 12:06 PM IST

Next Story