Q&A: S K Chaturvedi, CMD, Power Grid Corp

'We'll invest Rs 1 lakh crore in the next Plan'

Image
Mansi Taneja
Last Updated : Jan 20 2013 | 2:22 AM IST

Power Grid Corporation of India, the country’s largest transmission company, derives 94 per cent of revenue from this segment. It now plans to focus on its other businesses, of consultancy and telecom, aimed to contribute 15 per cent to revenue in the next five years. Chairman and managing director S K Chaturvedi talks to Mansi Taneja about the plans and growing consultancy business in markets abroad. Edited excerpts:

What investment will be done in the current financial year, also the last year of the 11th five-year Plan? What will be the company’s total capacity?
We had planned to invest almost Rs 55,000 crore in this Plan and we did Rs 38,000 crore in the four years. The rest of the amount, Rs 17,900 crore, will be invested in the current fiscal. Power Grid is the only company fully using its (budgeted) capex among all power PSUs.

We will be doing the target of 44,000 circuit-km lines of supply during the current Plan and will also achieve 28,000 Mw inter-regional capacity. We plan to invest over Rs 1 lakh crore in the 12th five-year plan.

Power Grid has picked up various consultancy assignments outside India. What are your expectations from this business?
About 94 per cent of our revenues come from transmission, which is a regulated sector. Consultancy and telecom segments are not regulated and we can thereby maximise our capacity in these two. We plan to go a big way in both these segments.

During the current year, we expect to finalise consultancy contracts with Myanmar, and with Sri Lanka for an undersea transmission project with India. We have recently signed a memorandum of understanding with Kenya for consultancy and we hope to bag more contracts this year.

You had recently leased out about 12,000 transmission towers for telecom use in four states. When do you plan to lease your towers on a pan-India basis? In the near future, how big do you think the telecom business will be for Power Grid?
The telecom business is more prospective in nature. The first avenue is to lease out towers. We will go pan-India by the end of the current fiscal; every quarter we will do leasing of towers in some areas. We have a total of 150,000 towers across the country.

We have also been selected as a major partner for laying out optical fibre for the government’s National Knowledge Network. We have also been shortlisted by the Unique Identification Developmental Authority for providing connection to panchayats through the country. We expect to increase our revenue from the consultancy and telecom business to 15 per cent from six per cent in the next five years. Every year, we are seeing a growth of 20-25 per cent on our revenues and we hope to continue that momentum.

How much do you plan to raise this year? And, how do you plan to fund the huge investment for the 12th Five-year plan?
We have Board approval for raising Rs 11,000 crore this fiscal through domestic bonds. We raised Rs 2,000 crore in the first tranche. Every quarter, we plan to raise Rs 2,000-2,500 crore. We had raised Rs 7,500 crore from the FPO (follow-on public offer) last year. Half the proceeds went to the government. Of the Rs 3,700 crore of the company from the FPO, around Rs 1,700 crore has been spent.

For the 12th plan, the funding will be done through internal resources, domestic bonds and bilateral funding. We are already in discussion with the World Bank and Asian Development Bank for raising $1 billion (Rs 4,432 crore) and $750 million (Rs 3,324 crore), respectively, and it will be finalised in the next three to four months. We also plan to go for another FPO in 2013-14 and raise Rs 5,000-7,000 crore.

What is the status of the undersea transmission line with Sri Lanka?
We have completed the feasibility report for the Indian side. Now, we will do the study for the Sri Lankan side for about Rs 58 lakh and submit the comprehensive project report within three months. Both reports will then go to the governments for a final decision, as in who will finance the undersea transmission link and what will be the mode of financing. We expect the 1,000 Mw capacity transmission line will come up in the 12th Five-year plan.

*Subscribe to Business Standard digital and get complimentary access to The New York Times

Smart Quarterly

₹900

3 Months

₹300/Month

SAVE 25%

Smart Essential

₹2,700

1 Year

₹225/Month

SAVE 46%
*Complimentary New York Times access for the 2nd year will be given after 12 months

Super Saver

₹3,900

2 Years

₹162/Month

Subscribe

Renews automatically, cancel anytime

Here’s what’s included in our digital subscription plans

Exclusive premium stories online

  • Over 30 premium stories daily, handpicked by our editors

Complimentary Access to The New York Times

  • News, Games, Cooking, Audio, Wirecutter & The Athletic

Business Standard Epaper

  • Digital replica of our daily newspaper — with options to read, save, and share

Curated Newsletters

  • Insights on markets, finance, politics, tech, and more delivered to your inbox

Market Analysis & Investment Insights

  • In-depth market analysis & insights with access to The Smart Investor

Archives

  • Repository of articles and publications dating back to 1997

Ad-free Reading

  • Uninterrupted reading experience with no advertisements

Seamless Access Across All Devices

  • Access Business Standard across devices — mobile, tablet, or PC, via web or app

More From This Section

First Published: Jul 23 2011 | 12:23 AM IST

Next Story