SC gives green signal to Sterlite and Posco projects in Orissa

Image
BS Reporter New Delhi
Last Updated : Jan 20 2013 | 9:59 PM IST

The Supreme Court today gave the green signal to the controversial Sterlite and Posco projects in Orissa, but imposed certain conditions to ensure the safety of environment and the welfare of the tribal inhabitants who would be uprooted by the mining giants.

The Anil Agarwal promoted Sterlite Industries will be able to proceed with its controverisal Rs 4,000 crore aluminium project in the ecologically fragile Niyamgiri hills. The company had sought clearance for diversion of 660.749 hectare of forest land for mining purposes to feed its alumina plant.

The special forest bench headed by Chief Justice K G Balakrishnan, which  allowed Sterlite to go ahead with bauxite mining, however, asked the Ministry of Environment and Forest to make sure that the project complied with the rules and regulations.

The other conditions imposed by the court in December last year will continue. According to them, 5 per cent of the profit of the company, or Rs 10 crore whichever is higher, would be ploughed back each year to keep ecological balance and for the welfare of those tribal people who would be displaced by the project. The Centrally Empowered Committee appointed by the Supreme Court and the “special purpose vehicle” set up after the December judgment would supervise the functioning of the project from the viewpoint of the environment and the rehabilitation of the project affected people.

The same bench cleared another controversial steel project promoted by Posco India, where the South Korean firm intends to invest Rs 51,000 crore. The project also includes a captive port at Paradeep.

The firm had signed an agreement with the Orissa government in 2005. The state-owned Orissa Mining Corporation (OMC) had agreed to supply uninterrupted iron ore and other minerals for its 12 mtpa project. when commissioned, it is projected to be the third largest steel plant in the world, producing annually 12 million tonnes of steel.

However, the project covers 1,650 hectares out of which 1,253 hectares are forest land.  This has created unrest among the tribal people and they have been agitating for nearly three years against the mega project.

*Subscribe to Business Standard digital and get complimentary access to The New York Times

Smart Quarterly

₹900

3 Months

₹300/Month

SAVE 25%

Smart Essential

₹2,700

1 Year

₹225/Month

SAVE 46%
*Complimentary New York Times access for the 2nd year will be given after 12 months

Super Saver

₹3,900

2 Years

₹162/Month

Subscribe

Renews automatically, cancel anytime

Here’s what’s included in our digital subscription plans

Exclusive premium stories online

  • Over 30 premium stories daily, handpicked by our editors

Complimentary Access to The New York Times

  • News, Games, Cooking, Audio, Wirecutter & The Athletic

Business Standard Epaper

  • Digital replica of our daily newspaper — with options to read, save, and share

Curated Newsletters

  • Insights on markets, finance, politics, tech, and more delivered to your inbox

Market Analysis & Investment Insights

  • In-depth market analysis & insights with access to The Smart Investor

Archives

  • Repository of articles and publications dating back to 1997

Ad-free Reading

  • Uninterrupted reading experience with no advertisements

Seamless Access Across All Devices

  • Access Business Standard across devices — mobile, tablet, or PC, via web or app

More From This Section

First Published: Aug 08 2008 | 5:33 PM IST

Next Story