Shadow over UltraTech limestone mining project in Chhattisgarh

The mined limestone will be used for the manufacturing of cement in the existing line

cement, construction
R Krishna Das Raipur
Last Updated : Mar 03 2017 | 4:07 PM IST
A limestone mining project of UltraTech Cement Limited in Chhattisgarh had landed into a spot after the state government on Friday cancelled a non-objection certificate granted for expediting the project.

The water resources department had given an NoC dated January 03, 2017 to the mining department, stating that the Pendraon reservoir adjoining the mine would not be affected by the mining activities. The mine, with a production capacity of four million tonnes per annum (mtpa), had been allotted to UtraTech Cement. The project is located across four villages in Tilda block of Raipur district and is interlinked with company’s integrated cement plant in the neighbouring Balodabazaar district. 

The mined limestone will be used for the manufacturing of cement in the existing line as well as proposed new line II of cement plant, cement (2.75 to 6.75 mtpa) and clinker (2.2 to 6.75 mtpa). In April 2015, the company has received environmental clearance for the project. The company had been granted mining lease but the execution of mining deed was under process.

After the NoC was granted, local villagers launched a vehement protest against the project stating that the catchment area of the reservoir was coming under the mining area. They said the existence of the reservoir was at the stake. Over 11,000 acres of land was irrigated from the reservoir water in the area.

"The NoC has been cancelled with immediate effect as the state government is committed not to diminish even an acre of irrigation land from Pendraon," Chhattisgarh's irrigation minister Brijmohan Agrawal said. Following the cancellation of the NoC, the mining activities would not be allowed in the area.

The company did not respond to a mail sent for its version on the issue.

BRIEF DESCRIPTION OF THE PROJECT

Nature of project: Limestone Mining Project.

Mining Lease area: 689.048 hectares

Production capacity: 4.0 mtpa.

Total Mineable Reserves: 120 million tonnes.

Life of Mine: 30 years

Total Project Cost: Rs 106 crore

Source: EIA Report

One subscription. Two world-class reads.

Already subscribed? Log in

Subscribe to read the full story →
*Subscribe to Business Standard digital and get complimentary access to The New York Times

Smart Quarterly

₹900

3 Months

₹300/Month

SAVE 25%

Smart Essential

₹2,700

1 Year

₹225/Month

SAVE 46%
*Complimentary New York Times access for the 2nd year will be given after 12 months

Super Saver

₹3,900

2 Years

₹162/Month

Subscribe

Renews automatically, cancel anytime

Here’s what’s included in our digital subscription plans

Exclusive premium stories online

  • Over 30 premium stories daily, handpicked by our editors

Complimentary Access to The New York Times

  • News, Games, Cooking, Audio, Wirecutter & The Athletic

Business Standard Epaper

  • Digital replica of our daily newspaper — with options to read, save, and share

Curated Newsletters

  • Insights on markets, finance, politics, tech, and more delivered to your inbox

Market Analysis & Investment Insights

  • In-depth market analysis & insights with access to The Smart Investor

Archives

  • Repository of articles and publications dating back to 1997

Ad-free Reading

  • Uninterrupted reading experience with no advertisements

Seamless Access Across All Devices

  • Access Business Standard across devices — mobile, tablet, or PC, via web or app

Next Story