The concerns from the potential developers of Ultra Mega Power Projects (UMPPs) come ahead of Thursday’s meeting of a ministerial panel to approve the newly proposed guidelines.
The two companies, in similar letters to power minister Jyotiraditya Scindia, have rejected the need for completely replacing the existing Standard Bidding Documents (SBDs) and have recommended only minor tweaking in the existing guidelines. “If the concerns raised are not addressed appropriately, we would not be able to put a competitive bid,” Tata Power Managing Director Anil Sardana wrote.
A key objection is over provisions on passing-on fuel supply risk to consumers. The new SBDs propose capping fuel price at the notified price of Coal India Ltd the state-owned monopoly coal supplier, in case of linked captive mines.
Fuel price in cased of imported coal from overseas captive mine is capped at 90% of global average with four% escalation. The companies have said these caps and escalations do not reflect the actual cost of coal incurred.
“The actual cost may be on lower side leading to windfall profits for the developer or on higher side leading to commercial impossibility for the developer to honor the contract,” Reliance Power Chief Executive Officer (CEO) J P Chalasani said. Also, according to Sardana, the provision would discourage developers to invest in coal mines abroad and structure bids based on market-linked coal prices.
Another key concern is over a proposed Design-Build-Finance-Operate-Transfer (DBFOT) model which allows the developers to purchase the project. “The model is not attractive in current economic scenario where investment in power sector has slowed down substantially and developers are uncomfortable committing capital as a mere contractor,” Chalasani wrote.
The companies have also objected to the numerous possibilities of terminating Power Purchase Agreement (PPA) by procurers.
The draft provides for termination even in the event of payment default by the procurer, making business proposition “very unpredictable and one-sided”, according to Sardana. He also said the qualification criteria set out in the SBDs, recommending short-listing of only top seven bidders for the Request for Proposal (RFP) stage, are very restrictive.
Chalasani also said the new SBD, in its present form, could discourage Reliance Power from participation or offer competitive tariff. The government had notified the existing bidding guidelines in 2006. Since then, over 40,000 Mw of new capacity has come on stream.
The new bidding parameters will determine the success rate of the government’s ambitious UMPP scheme under which nine projects, each of them with 4,000 Mw capacity and around Rs 20,000 crore investment, are to be set up across states.
You’ve reached your limit of {{free_limit}} free articles this month.
Subscribe now for unlimited access.
Already subscribed? Log in
Subscribe to read the full story →
Smart Quarterly
₹900
3 Months
₹300/Month
Smart Essential
₹2,700
1 Year
₹225/Month
Super Saver
₹3,900
2 Years
₹162/Month
Renews automatically, cancel anytime
Here’s what’s included in our digital subscription plans
Exclusive premium stories online
Over 30 premium stories daily, handpicked by our editors


Complimentary Access to The New York Times
News, Games, Cooking, Audio, Wirecutter & The Athletic
Business Standard Epaper
Digital replica of our daily newspaper — with options to read, save, and share


Curated Newsletters
Insights on markets, finance, politics, tech, and more delivered to your inbox
Market Analysis & Investment Insights
In-depth market analysis & insights with access to The Smart Investor


Archives
Repository of articles and publications dating back to 1997
Ad-free Reading
Uninterrupted reading experience with no advertisements


Seamless Access Across All Devices
Access Business Standard across devices — mobile, tablet, or PC, via web or app
)