AERB nod for Kudankulam project likely

The first approach to criticality means the reaction of neutron bombardment to uranium atom will start

Sanjay Jog Mumbai
Last Updated : May 08 2013 | 1:09 AM IST
The first unit of the Kudankulam nuclear power project in Tamil Nadu may soon get regulatory clearance for its first approach to criticality.  When the atom-splitting reactor of a nuclear power plant is operating normally, it is said to be “critical” or in a state of “criticality”.

The Kudankulam unit is now awaiting clearance from the Atomic Energy Regulatory Board (AERB) for its first approach. One more step is required to be crossed towards criticality. AERB will give its nod to Nuclear Power Corp of India Ltd (NPCIL), which is setting up the Kudankulam plant after a satisfactory safety review, a top official said.   

“AERB is currently reviewing the first approach to criticality. A high level observer team is at the project site, which is giving daily reports to our headquarters, which are subsequently reviewed,” AERB secretary R Bhattacharya told Business Standard.

AERB secretary’s statement is crucial when the Kudankulam project site director RS Sundar on Monday had told this correspondent that NPC has already approached AERB to seek various clearances. He had informed that the Kudankulam project may achieve criticality by end of May and after 25 days the power generation will begin.

As far as the apex court’s directives on monitoring and periodical reviews, Bhattacharya said this will be fully complied with. “AERB has put in place a quarterly inspection of each nuclear power project in the country. This will also be followed in case of Kudankulam project,” he noted.

Bhattacharya explained that the quarterly inspection consists of physical verification of site, documents by expert members.
Meanwhile, AERB chairman SS Bajaj said as per the well established regulatory process of AERB, commissioning stage of a nuclear power plant (NPP) involves conducting series of checks and tests, system wise and also in an integrated manner to ensure that all the systems perform as per the design intent. The results of various tests conducted at each stage are reviewed in AERB. Only after satisfactory review, permission for proceeding to subsequent stage is given.

“Granting stage wise clearance/s, which may further have sub-stages, is an intrinsic regulatory measure to ensure that previous stages have been completed as per the approved procedures and the compliance of the same has been established before issuance of clearance of the next stage.  Once any shortcoming is noticed in any system while checking the same, corrective measures are recommended to Nuclear Power Corporation and only after a satisfactory review of all associated safety concerns AERB grants subsequent clearances,” Bajaj said.
*Subscribe to Business Standard digital and get complimentary access to The New York Times

Smart Quarterly

₹900

3 Months

₹300/Month

SAVE 25%

Smart Essential

₹2,700

1 Year

₹225/Month

SAVE 46%
*Complimentary New York Times access for the 2nd year will be given after 12 months

Super Saver

₹3,900

2 Years

₹162/Month

Subscribe

Renews automatically, cancel anytime

Here’s what’s included in our digital subscription plans

Exclusive premium stories online

  • Over 30 premium stories daily, handpicked by our editors

Complimentary Access to The New York Times

  • News, Games, Cooking, Audio, Wirecutter & The Athletic

Business Standard Epaper

  • Digital replica of our daily newspaper — with options to read, save, and share

Curated Newsletters

  • Insights on markets, finance, politics, tech, and more delivered to your inbox

Market Analysis & Investment Insights

  • In-depth market analysis & insights with access to The Smart Investor

Archives

  • Repository of articles and publications dating back to 1997

Ad-free Reading

  • Uninterrupted reading experience with no advertisements

Seamless Access Across All Devices

  • Access Business Standard across devices — mobile, tablet, or PC, via web or app

More From This Section

First Published: May 08 2013 | 12:34 AM IST

Next Story