Power Min mandates 40% renewable purchase obligation for thermal plants

Ministry of Power has mandated new coal or lignite-based thermal plants to either set up renewable energy capacity equivalent to at least 40 per cent of the thermal plant's capacity

power, electricity, thermal, plant
Press Trust of India New Delhi
2 min read Last Updated : Mar 07 2023 | 8:19 PM IST

The Ministry of Power has mandated new coal or lignite-based thermal plants to either set up renewable energy capacity equivalent to at least 40 per cent of the thermal plant's capacity or procure that much supply of green energy under renewable purchase obligation.

Earlier this month the power ministry amended the Tariff Policy 2016 under Electricity Act 2003 to impose the renewable purchase obligation of 40 per cent for the new coal or lignite-based thermal power plants to be set up from April 1, 2023 onwards, showed a notification.

"... any generating company establishing a coal/lignite-based thermal generating station and having the Commercial Operation Date (COD) of the project on or after April 1, 2023 shall be required to establish renewable energy generating capacity (in MW) i.e. Renewable Generation Obligation (RGO) of a minimum of 40 per cent of the capacity of the thermal generating station or procure and supply renewable energy equivalent to such capacity," it explained.

A coal/lignite based thermal generating station with COD of the project between April 1, 2023 and March 31, 2025 shall be required to comply with RGO of 40 per cent by April 1, 2025.

Any other coal/lignite based thermal generating station with COD of the project after April 1, 2025 shall be required to comply with RGO of 40 per cent by the Commercial Operation Date.

Further, a captive coal/lignite-based thermal generating station shall be exempt from requirement of RGO subject to its fulfilling Renewable Purchase Obligations as notified by the central government, it stated.

This assumes significance in view of India's ambitious target of having 500 MW of renewable energy capacity by 2030.

India had 121549.52 MW of renewable energy capacity excluding large hydro (over 25 MW) as on January 31, 2023. This includes 63893.83 MW solar, 41983.18 MW wind energy and 10209.81 MW of biomass or co-generation power.

(Only the headline and picture of this report may have been reworked by the Business Standard staff; the rest of the content is auto-generated from a syndicated feed.)

*Subscribe to Business Standard digital and get complimentary access to The New York Times

Smart Quarterly

₹900

3 Months

₹300/Month

SAVE 25%

Smart Essential

₹2,700

1 Year

₹225/Month

SAVE 46%
*Complimentary New York Times access for the 2nd year will be given after 12 months

Super Saver

₹3,900

2 Years

₹162/Month

Subscribe

Renews automatically, cancel anytime

Here’s what’s included in our digital subscription plans

Exclusive premium stories online

  • Over 30 premium stories daily, handpicked by our editors

Complimentary Access to The New York Times

  • News, Games, Cooking, Audio, Wirecutter & The Athletic

Business Standard Epaper

  • Digital replica of our daily newspaper — with options to read, save, and share

Curated Newsletters

  • Insights on markets, finance, politics, tech, and more delivered to your inbox

Market Analysis & Investment Insights

  • In-depth market analysis & insights with access to The Smart Investor

Archives

  • Repository of articles and publications dating back to 1997

Ad-free Reading

  • Uninterrupted reading experience with no advertisements

Seamless Access Across All Devices

  • Access Business Standard across devices — mobile, tablet, or PC, via web or app

More From This Section

Topics :Power ministryThermal Power

First Published: Mar 07 2023 | 8:19 PM IST

Next Story