“Supply of power could obviously be increased because the country has achieved a reasonable level of installed capacity, which is rising further. But everything will come to nought if the distribution sector continues to be managed in the manner that it has been so far,” says the advisory group’s report, which Business Standard has reviewed.
| 24x7 POWER FOR ALL: THE WAY AHEAD |
|
The committee has emphasised that availability of transmission infrastructure has to be ahead of power generation, so that the incidence of transmission bottlenecks is eliminated.
The total investment for development of transmission system is estimated at about Rs 2 lakh- crore. By 2018-19, an additional investment of Rs 1.2 lakh-crore will be required.
So, the committee has laid stress on private participation in T&D as an imperative. “While the proportion of generation capacity by the private sector is of the order of 35 per cent, the private-sector transmission capacity is only three per cent. This needs to be enhanced. New projects need to be identified and bids offered,” says the report. Hinting at a decrease in Power Grid Corporation’s monopoly, the committee has suggested apart from the reserved list of projects given for strategic reasons, the projects coming to the state-run giant should be as few as possible.
“Beyond this small list, all other projects should be opened up for development by the public, as well as the private sector. It should be prepared at the earliest, as this will help accelerate the pace of development of transmission projects,” says the report.
The high-powered committee has advised the best way to tackle the power supply situation in the country is to have a time-bound plan to strengthen the transmission and sub-transmission infrastructure. It says: “Distribution sector reform holds the key to ‘24x7 power supply’, and it needs institutional changes, including privatisation and public-private partnerships.”
The annual financial losses of state utilities stand at close to Rs 80,000 crore. The committee has suggested the state governments look at alternative strategies, such as capital restructuring, partial takeover of load and regulatory intervention for cost-reflective rates.
“In the states where access is already reasonably good, the target for connected loads could be one year. In the next category (the states where access is not so good), it could be two years; and in the last category, three years,” says the report. Overall, the target for transmission to strengthen even in the remotest corners of the country is five to seven years.
The committee has also asked for a long-term transmission plan, of 20-25 years, with a mechanism for close monitoring of development.
“The mechanism to identify critical transmission constraints, formulate specific projects and have those executed in the most effective manner, needs to be put in place at the earliest. Guidelines will be issues by the power ministry within a month,” says the report.
You’ve reached your limit of {{free_limit}} free articles this month.
Subscribe now for unlimited access.
Already subscribed? Log in
Subscribe to read the full story →
Smart Quarterly
₹900
3 Months
₹300/Month
Smart Essential
₹2,700
1 Year
₹225/Month
Super Saver
₹3,900
2 Years
₹162/Month
Renews automatically, cancel anytime
Here’s what’s included in our digital subscription plans
Exclusive premium stories online
Over 30 premium stories daily, handpicked by our editors


Complimentary Access to The New York Times
News, Games, Cooking, Audio, Wirecutter & The Athletic
Business Standard Epaper
Digital replica of our daily newspaper — with options to read, save, and share


Curated Newsletters
Insights on markets, finance, politics, tech, and more delivered to your inbox
Market Analysis & Investment Insights
In-depth market analysis & insights with access to The Smart Investor


Archives
Repository of articles and publications dating back to 1997
Ad-free Reading
Uninterrupted reading experience with no advertisements


Seamless Access Across All Devices
Access Business Standard across devices — mobile, tablet, or PC, via web or app
)