Ministry of Statistics and Programme Implementation monitors infrastructure projects worth Rs 150 and above.
The total original cost of implementing 1,257 projects was Rs 15,76,903.56 crore and their anticipated completion cost is likely to be Rs 17,49,274.62 crore, cost overrun of Rs 1,72,371.06 crore (10.93 per cent of the original), the ministry's flash report for July this year has stated.
Also Read
The 1,257 projects in question include 331 that reported cost overrun and 274 time escalation.
"Out of a total of 1,257 projects, 2 projects have reported completion and 10 new projects have been initiated on the monitor of this ministry during the current month (July). Of these, 11 projects are ahead of schedule, 304 are on schedule and 274 are delayed, 331 projects are showing cost overrun and 92 projects are showing both time and cost overrun with respect to original implementation schedules."
However, the report said that the number of delayed projects decreases to 215 if delay is calculated with reference to latest revised schedules of completion.
The report also highlights that for 668 projects, the original/anticipated commissioning dates were not reported by the authorities concerned.
It further said that out of 274 delayed projects, 47 have overall delay in the range of 1 to 12 months, 59 have delay in the range of 13 to 24 months, 101 have delay in the range of 25 to 60 months and 67 have delay of 61 months and above.
Of the 1,257 projects, 372 are mega projects worth Rs 1,000 crore and above.
The total original cost of implementation of these 372 projects was Rs 12,17,096.27 crore and their anticipated completion cost is likely to be Rs 13,60,528.92 crore, which reflects overall cost overruns of Rs 1,43,432.65 crore (11.78 per cent of the original cost).
The expenditure incurred on these mega projects till July was Rs 5,70,750.91 crore, which is 41.95 per cent of the anticipated cost of the projects.
Out of the 372 mega projects, 130 have cost overruns with respect to original cost and the number of such projects decreased to 103 when cost overrun is calculated on the basis of revised cost.
The report attributes the time overrun to a host of issues including delay in land acquisition, forest clearance, supply of equipment, funds constraints, the Maoist incursion, legal cases and law and order situation.
(Only the headline and picture of this report may have been reworked by the Business Standard staff; the rest of the content is auto-generated from a syndicated feed.)
You’ve reached your limit of {{free_limit}} free articles this month.
Subscribe now for unlimited access.
Already subscribed? Log in
Subscribe to read the full story →
Smart Quarterly
₹900
3 Months
₹300/Month
Smart Essential
₹2,700
1 Year
₹225/Month
Super Saver
₹3,900
2 Years
₹162/Month
Renews automatically, cancel anytime
Here’s what’s included in our digital subscription plans
Exclusive premium stories online
Over 30 premium stories daily, handpicked by our editors


Complimentary Access to The New York Times
News, Games, Cooking, Audio, Wirecutter & The Athletic
Business Standard Epaper
Digital replica of our daily newspaper — with options to read, save, and share


Curated Newsletters
Insights on markets, finance, politics, tech, and more delivered to your inbox
Market Analysis & Investment Insights
In-depth market analysis & insights with access to The Smart Investor


Archives
Repository of articles and publications dating back to 1997
Ad-free Reading
Uninterrupted reading experience with no advertisements


Seamless Access Across All Devices
Access Business Standard across devices — mobile, tablet, or PC, via web or app
)