In a much awaited ruling, Central Electricity Regulatory Commission (CERC) has allowed higher tariff as well as compensation of Rs 329.45 crore for Tata Power's 4,000-MW Mundra project in Gujarat.
The regulator has ruled for a compensatory tariff of Rs 0.524 per kWh for the project from the period beyond April 1, 2013, which has to be borne by the five states -- Gujarat, Maharashtra, Rajasthan, Haryana and Punjab.
Also Read
Mahavitaran is Maharashtra's power distribution company (discom).
Sources at the discom said if the order is implemented, it would have to bear an additional burden of about 45 to 50 paise per unit of electricity.
Discoms in Gujarat, Rajasthan, Haryana and Punjab could not be immediately contacted.
Coastal Gujarat Power Ltd (CGPL), which is implementing the Mundra Project, has agreements with the five states for selling power from the plant at a price of Rs 2.26 per unit.
CGPL is a wholly-owned subsidiary of Tata Power.
The CERC ruling, made public on Saturday, came on a plea from Tata Power seeking relief for the project due to price rise in Indonesian coal that is used to fire the plant.
The Mundra project has been seeing significant losses on account of increased price of imported coal.
Describing the order as "balanced, Tata Power in a statement yesterday said it provides partial relief to Mundra UMPP.
The decision of CERC was awaited to make Mundra viable, which had got impacted due to no fault of the firm, but due to change of law at Indonesia as also other coal exporting countries and an unprecedented rise which could not have been perceived, it added.
In a separate order, CERC granted nearly Rs 830 crore compensation for Adani Power's 4,620 MW Mundra plant.
Gujarat has to pay Rs 420.24 crore while Haryana has to shell out Rs 409.51 crore as compensation from the commissioning date till March 31, 2013, the order said. A formula for compensatory tariff for period starting from April 1, 2013 has been decided by CERC.
This order pertains to one of Adani Power's PPA (February 2, 2007) with Gujarat Urja Vikas Nigam Ltd for 1,000 MW and two PPAs (August 7, 2008) with Haryana utilities -- Uttar Haryana Bijli Vidyut Nigam Ltd and Dakshin Haryana Bijli Vidyut Nigam Ltd.
You’ve reached your limit of {{free_limit}} free articles this month.
Subscribe now for unlimited access.
Already subscribed? Log in
Subscribe to read the full story →
Smart Quarterly
₹900
3 Months
₹300/Month
Smart Essential
₹2,700
1 Year
₹225/Month
Super Saver
₹3,900
2 Years
₹162/Month
Renews automatically, cancel anytime
Here’s what’s included in our digital subscription plans
Exclusive premium stories online
Over 30 premium stories daily, handpicked by our editors


Complimentary Access to The New York Times
News, Games, Cooking, Audio, Wirecutter & The Athletic
Business Standard Epaper
Digital replica of our daily newspaper — with options to read, save, and share


Curated Newsletters
Insights on markets, finance, politics, tech, and more delivered to your inbox
Market Analysis & Investment Insights
In-depth market analysis & insights with access to The Smart Investor


Archives
Repository of articles and publications dating back to 1997
Ad-free Reading
Uninterrupted reading experience with no advertisements


Seamless Access Across All Devices
Access Business Standard across devices — mobile, tablet, or PC, via web or app
)