Coalmin for early meet of GoM to resolve green issues

Image
Press Trust of India New Delhi
Last Updated : Jan 20 2013 | 2:09 AM IST

Peeved at delays in green clearances hurting potential annual coal production of about 660 million tonne, the Coal Ministry has requested the Finance Ministry to finalise an early date for the third meeting of the Group of Ministers (GoM) on coal.

The GoM, headed by Finance Minister Pranab Mukherjee, was constituted at the behest of Prime Minister Manmohan Singh in February to sort out inter-ministerial tussles on the environment norms affecting projects, especially in the coal sector.

The 12-member GoM had met twice in February and April but could not reach at any conclusion.

"We have written a letter to the Finance Ministry asking it to finalise the date for the third meeting of the GoM on coal," a senior Coal Ministry official said.

The third meeting which was scheduled to be held last month could not take place and a final date is yet to be fixed, the official said, adding that the Ministry has requested for an early date.

The Ministry of Environment and Forest (MoEF), in 2009, had categorised 203 coal blocks as 'no go' mining zone, which according to the Coal Ministry has stalled a potential production of about 660 million tonne per annum (MTPA).

The output from these 203 blocks can generate around 1.3 lakh MW of power per annum as per the estimates of the Coal Ministry.

The Coal Ministry has been demanding permission to mine in at least 90% of these 203 blocks to meet the ever widening demand-supply gap of the dry fuel.

The shortage of coal is likely to reach 137 MT this fiscal and 200 MT by FY17.

In the second meeting of the GoM, the Environment Ministry had proposed that it was "prepared to consider revised 'go/ no-go' approach that will free 71% of area in the nine coalfields (203 blocks)."

Originally, the Environment Ministry had proposed to free only 53% of the area in the nine coalfields.

*Subscribe to Business Standard digital and get complimentary access to The New York Times

Smart Quarterly

₹900

3 Months

₹300/Month

SAVE 25%

Smart Essential

₹2,700

1 Year

₹225/Month

SAVE 46%
*Complimentary New York Times access for the 2nd year will be given after 12 months

Super Saver

₹3,900

2 Years

₹162/Month

Subscribe

Renews automatically, cancel anytime

Here’s what’s included in our digital subscription plans

Exclusive premium stories online

  • Over 30 premium stories daily, handpicked by our editors

Complimentary Access to The New York Times

  • News, Games, Cooking, Audio, Wirecutter & The Athletic

Business Standard Epaper

  • Digital replica of our daily newspaper — with options to read, save, and share

Curated Newsletters

  • Insights on markets, finance, politics, tech, and more delivered to your inbox

Market Analysis & Investment Insights

  • In-depth market analysis & insights with access to The Smart Investor

Archives

  • Repository of articles and publications dating back to 1997

Ad-free Reading

  • Uninterrupted reading experience with no advertisements

Seamless Access Across All Devices

  • Access Business Standard across devices — mobile, tablet, or PC, via web or app

More From This Section

First Published: May 26 2011 | 6:52 PM IST

Next Story