NHAI spruces up land acquisition activity prior to award of contracts

The roads ministry has set a target of awarding 7,000-km road projects during FY15

Mansi Taneja New Delhi
Last Updated : Jun 22 2014 | 2:29 AM IST
Aiming to reduce delays in the award of road projects, the National Highways Authority of India (NHAI) spent Rs 6,870 crore in 2013-14 for acquiring land for future projects, which is about 49 per cent higher than what was spent in the previous year. According to a senior NHAI official, about 8,300 hectares were acquired in 2013-14, against 6,700 hectares at4,600 crore in 2012-13. "This will reduce the delays in the award of projects as the main issue is acquisition of land," the official said.

The Union Ministry of Road Transport and Highways has recently decided to award projects after acquiring a certain percentage of the land. In government-funded projects - through the EPC (engineering- procurement-construction) route, about 90 per cent of land is acquired before the appraisal stage. While in the BOT (build-operate-transfer) projects, 60 per cent of land has to be acquired in the appraisal stage and 80 per cent during the award stage.

Due to the economic slowdown over the last few years, the award of contracts for national highways has slowed down. Besides issues related to environment and forest clearances, land acquisition has seen major problems. Many road projects are stalled by developers running short of cash and the government has even allowed them to reschedule the payment of premiums under a new policy.

"The bad patch seems to be over now. The financial markets are expected to rise and bounce back. This will revive interest in the PPP (public-private-partnership) model," added another official.

The roads ministry has set a target of awarding 7,000 km worth of road projects during the financial year 2014-15, under both BOT and EPC modes. For 2013-14, about 3,169 km of projects were awarded against a target of 7,500 km as there were less takers for PPP projects.

The government funds the entire project under EPC and a developer undertakes the necessary construction work. BOT requires a private-sector developer to raise and invest money for the construction of roads at its own risk and NHAI acquires land for the project.
*Subscribe to Business Standard digital and get complimentary access to The New York Times

Smart Quarterly

₹900

3 Months

₹300/Month

SAVE 25%

Smart Essential

₹2,700

1 Year

₹225/Month

SAVE 46%
*Complimentary New York Times access for the 2nd year will be given after 12 months

Super Saver

₹3,900

2 Years

₹162/Month

Subscribe

Renews automatically, cancel anytime

Here’s what’s included in our digital subscription plans

Exclusive premium stories online

  • Over 30 premium stories daily, handpicked by our editors

Complimentary Access to The New York Times

  • News, Games, Cooking, Audio, Wirecutter & The Athletic

Business Standard Epaper

  • Digital replica of our daily newspaper — with options to read, save, and share

Curated Newsletters

  • Insights on markets, finance, politics, tech, and more delivered to your inbox

Market Analysis & Investment Insights

  • In-depth market analysis & insights with access to The Smart Investor

Archives

  • Repository of articles and publications dating back to 1997

Ad-free Reading

  • Uninterrupted reading experience with no advertisements

Seamless Access Across All Devices

  • Access Business Standard across devices — mobile, tablet, or PC, via web or app

More From This Section

First Published: Jun 21 2014 | 11:50 PM IST

Next Story