Nuclear Power Corp hopes to commission first unit by Sept

Image
BS Reporter Mumbai
Last Updated : Jan 21 2013 | 2:31 AM IST

The state-run Nuclear Power Corporation (NPC) has lost power generation of 6,000 million units and is incurring a loss of Rs 5 crore daily due to the stoppage of work at the 2,000 Mw Kudankulam nuclear project.

The company, which has so far incurred expenditure of Rs 14,000 crore, expects six to eight month from the day the work starts for the commissioning of first unit of 1,000 Mw, while the second unit of equal capacity would take another eight to nine months.

However, NPC has said it depends on the Tamil Nadu government's clearance, the time required to re-mobilise the contractors (Indian and Russian) and the over 5,000 contract workers.

Despite the loss, NPC is expected to achieve generation of 32,000 million units by the end of March. Currently, 20 of NPC's plants are operating at 90 per cent availability, and at 78-79 per cent plant load factor due to the unavailability of adequate fuel.

NPC director (technical) S A Bhardwaj told reporters that since mid-October last year, when the protests were launched, around 100 employees were able to report for duties inside the plant and carry out maintenance job.

"Once the Tamil Nadu government gives clearance, NPC will carry out a thorough survey of the plant and launch the necessary works for the completion of the first unit. We will have to inspect whether there is a corrosion or fungus, which will take two to three months. We are quite close to zero date to restart work," he said.

Despite the delays, Bhardwaj said the per unit tariff of Kudankulam power would be less than Rs 3.

The first unit of the project was to be commissioned last December and the second unit in March. The schedule was disrupted after villagers and NGOs launched protests raising safety concerns.

Bhardwaj said the experts panel appointed by the Central government and similar group formed by the state government have addressed all issues relating to safety and security of the project. The panels concluded the plant has adequate safety applications.

*Subscribe to Business Standard digital and get complimentary access to The New York Times

Smart Quarterly

₹900

3 Months

₹300/Month

SAVE 25%

Smart Essential

₹2,700

1 Year

₹225/Month

SAVE 46%
*Complimentary New York Times access for the 2nd year will be given after 12 months

Super Saver

₹3,900

2 Years

₹162/Month

Subscribe

Renews automatically, cancel anytime

Here’s what’s included in our digital subscription plans

Exclusive premium stories online

  • Over 30 premium stories daily, handpicked by our editors

Complimentary Access to The New York Times

  • News, Games, Cooking, Audio, Wirecutter & The Athletic

Business Standard Epaper

  • Digital replica of our daily newspaper — with options to read, save, and share

Curated Newsletters

  • Insights on markets, finance, politics, tech, and more delivered to your inbox

Market Analysis & Investment Insights

  • In-depth market analysis & insights with access to The Smart Investor

Archives

  • Repository of articles and publications dating back to 1997

Ad-free Reading

  • Uninterrupted reading experience with no advertisements

Seamless Access Across All Devices

  • Access Business Standard across devices — mobile, tablet, or PC, via web or app

More From This Section

First Published: Mar 11 2012 | 12:37 AM IST

Next Story