UP aims to finish 2 highways before 2022 polls, steps up land acquisition

Land acquisition for the 353-km Purvanchal Expressway and the 296-km Bundelkhand Expressway is in top gear, say officials.

Yamuna Expressway Project
UP aims to build more highways like Yamuna Expressway pictured in this story.
Virendra Singh Rawat Lucknow
2 min read Last Updated : May 12 2019 | 6:33 PM IST
Uttar Pradesh's BJP government aims to finish before the 2022 state elections two highways that will cost Rs 37,000 crore and require land acquisition of nearly 8,000 hectares.

Land acquisition for the 353-km Purvanchal Expressway and the 296-km Bundelkhand Expressway is in top gear, said government officials.

The Purvanchal Expressway, which is under construction, will cost Rs 23,000 crore and is projected to be completed by August-September 2020. Competitive bidding for Bundelkhand Expressway, which will cost Rs 14,000 crore, will start after the model code of conduct for Lok Sabha elections is over.

 

More than 96 per cent of the 4,332 hectares needed for the Purvanchal Expressway has been acquired, according to UP Expressway Industrial Development Authority (UPEIDA), the nodal agency for the two projects.

As much as 60 per cent of the 3,642 hectares need for the Bundelkhand Expressway has been acquired. It will connect the backward region of Bundelkhand, which comprises cities like Jhansi and Banda, with mainland Uttar Pradesh and the National Capital Region (NCR) via other highways like the Agra-Lucknow Expressway and the Agra-Greater Noida Yamuna Expressway.

Purvanchal Expressway will pass through nine districts: Lucknow, Barabanki, Faizabad, Ambedkar Nagar, Amethi, Sultanpur, Azamgarh, Mau, and Ghazipur.

The state government in January cleared the proposed 91-km Gorakhpur Link Expressway, which is estimated to cost an additional Rs 5,555 crore and which will link Gorakhpur with the Purvanchal Expressway.

The Bundelkhand Expressway will pass through Jhansi, Banda, Hamirpur, Mahoba, Jalaun, Auraiya and Etawah districts. It will touch Agra-Lucknow Expressway at Etawah.

The process for acquiring the remaining land for the two projects is likely to be completed in a few weeks, according to a senior UPEIDA official.

One subscription. Two world-class reads.

Already subscribed? Log in

Subscribe to read the full story →
*Subscribe to Business Standard digital and get complimentary access to The New York Times

Smart Quarterly

₹900

3 Months

₹300/Month

SAVE 25%

Smart Essential

₹2,700

1 Year

₹225/Month

SAVE 46%
*Complimentary New York Times access for the 2nd year will be given after 12 months

Super Saver

₹3,900

2 Years

₹162/Month

Subscribe

Renews automatically, cancel anytime

Here’s what’s included in our digital subscription plans

Exclusive premium stories online

  • Over 30 premium stories daily, handpicked by our editors

Complimentary Access to The New York Times

  • News, Games, Cooking, Audio, Wirecutter & The Athletic

Business Standard Epaper

  • Digital replica of our daily newspaper — with options to read, save, and share

Curated Newsletters

  • Insights on markets, finance, politics, tech, and more delivered to your inbox

Market Analysis & Investment Insights

  • In-depth market analysis & insights with access to The Smart Investor

Archives

  • Repository of articles and publications dating back to 1997

Ad-free Reading

  • Uninterrupted reading experience with no advertisements

Seamless Access Across All Devices

  • Access Business Standard across devices — mobile, tablet, or PC, via web or app

Next Story