SJVN achieves financial closure for 66 MW Dhaulasidh Hydro Power project

Explore Business Standard

The project has already commenced its construction activities since May 2021 and moving fast forward to generate 304 Million unit in a 90% dependable year of clean Hydro Power from FY2025-26 with levelized tariff of 4.46/Kwh.The total project cost of 688 crore of DSHEP has to be financed through a Debt Equity Ratio of 80:20.
Powered by Capital Market - Live News
Disclaimer: No Business Standard Journalist was involved in creation of this content
First Published: Apr 18 2022 | 6:01 PM IST