Builders can't end deals if their demands aren't met

Apartment buyers are often put in a tight spot by developers who demand more money after initial payments

Image
Jehangir Gai
Last Updated : Jan 24 2013 | 2:10 AM IST

Real estate developers who sell apartments during recession sometimes try to extract money later, at the time of possession, or try to illegally end the agreement with buyers on some pretext, so that the same flat can be re-sold at a higher price. In a recent judgment, the Maharashtra State Commission has come down heavily on one such builder.

Ameet Arjundas Israni and his wife, Meenal, had booked a flat with Bhumiraj Constructions in an under-construction building in Navi Mumbai. The cost of the 1,249-sq ft terrace flat was Rs 34.65 lakh. The agreement was stamped and registered for Rs 1.79 lakh. Parking space was sold for Rs 1 lakh.

After the buyer paid a substantial amount, the builder demanded interest for stage-wise construction for areas constructed. The Isranis refused to pay, as the agreement was prospective in nature and did not provide for retrospective interest prior to its execution. The builder terminated the deal for this but still sent a demand letter for the subsequent instalments and accepted payment.

CHECKLIST FOR FLAT PURCHASERS
1. An apartment buyer has the right to demand inspection of documents before agreeing to buy
2. The buyer must ascertain the identity and the status of the builder — whether the builder is an individual, a registered partnership firm or a company
3. The buyer must check the title to the land to ascertain if it is freehold or leasehold, and whether the builder has the title or the right to develop the land. If the land is leasehold, the tenure of such a lease and its assignment must be verfied
4. A builder cannot demand more than 20 per cent of the total purchase price of the flat before executing a written agreement
5. The agreement must specify the carpet area
6. The agreement must specify the date of possession

The Isranis paid 97 per cent of the agreed amount, and only three per cent was left. It was payable during handing over of the flat. Construction of the building was completed but the builder refused to give possession, claiming the agreement had been terminated.

The Isranis filed a consumer complaint on February 3, 2006, seeking possession of the flat and compensation for delay. During the pendency of the case, the state commission granted an interim injunction restraining the builder from creating any third party interest in the flat.

The builder filed a suit before the civil judge in Thane on April 18, 2006, for a direction that the agreement had been validly terminated. The court dismissed the suit, saying the builder had not been able to prove the Isranis had delayed payments and so the builder did not have the right to demand Rs 2,50,177 as interest. The court concluded the builder’s demand was against the terms of the agreement, and the deal termination was illegal.

The builder defended the consumer court case by claiming the deal was validly terminated. The builder contended an appeal had been filed against the civil court’s judgment and so it ought to be disregarded, though no order had been passed in appeal.

In the judgment dated October 11, 2012, the state commission observed that even though the agreement specified a schedule for payment, it was silent on if it would be retrospectively applicable to an agreement executed after the construction was underway.

Also, there was no clause in the agreement providing for delay in payments due prior to execution of the agreement. The commission noted the payments were made on time after execution of the agreement.

Accordingly, the state commission held the termination of the agreement was illegal, and constituted a deficiency in service. The commission said the Isranis should be compensated for being deprived of a shelter for over six years, despite having paid 97 per cent of the agreed consideration.

The panel directed Bhumiraj Construction and its partners to accept the balance three per cent consideration of Rs 1,03,950 and hand over vacant possession of the flat without demanding delayed payment interest. The order was to be complied within two months of receipt of the balance amount.

The builder and its partners were also held liable to pay Rs 5 lakh as compensation for the mental harassment and agony caused. The amount would attract an interest of 12 per cent a year if the amount was not paid within two months.

The author is a consumer activist

*Subscribe to Business Standard digital and get complimentary access to The New York Times

Smart Quarterly

₹900

3 Months

₹300/Month

SAVE 25%

Smart Essential

₹2,700

1 Year

₹225/Month

SAVE 46%
*Complimentary New York Times access for the 2nd year will be given after 12 months

Super Saver

₹3,900

2 Years

₹162/Month

Subscribe

Renews automatically, cancel anytime

Here’s what’s included in our digital subscription plans

Exclusive premium stories online

  • Over 30 premium stories daily, handpicked by our editors

Complimentary Access to The New York Times

  • News, Games, Cooking, Audio, Wirecutter & The Athletic

Business Standard Epaper

  • Digital replica of our daily newspaper — with options to read, save, and share

Curated Newsletters

  • Insights on markets, finance, politics, tech, and more delivered to your inbox

Market Analysis & Investment Insights

  • In-depth market analysis & insights with access to The Smart Investor

Archives

  • Repository of articles and publications dating back to 1997

Ad-free Reading

  • Uninterrupted reading experience with no advertisements

Seamless Access Across All Devices

  • Access Business Standard across devices — mobile, tablet, or PC, via web or app

More From This Section

First Published: Dec 10 2012 | 12:47 AM IST

Next Story