CAG pulls up Maha govt over delay in water transport system

Image
Press Trust of India Mumbai
Last Updated : Aug 05 2016 | 7:42 PM IST
The Comptroller and Auditor General has rapped the Maharashtra government for its "indecision" in implementing of the water transport system in Mumbai, which has led to a "wasteful" expenditure of Rs 20.95 crore.
The report says that the state government had in June 1999 appointed Maharashtra Maritime Board (MMB) as the implementing agency for the work of developing passenger water transport system along the Mumbai coast.
The MMB conducted detailed surveys and drew designs and invited tenders on Build-Own-Operate-Transfer (BOOT) basis.
"But then suddenly it was decided to transfer the project to the Maharashtra State Road Development Corporation Limited (MSRDCL)," the CAG report said.
Following the transfer of project, MSRDCL also prepared plans and detailed engineering drawings and obtained all the required permissions, the CAG said.
The CAG said this in its report tabled in both the Houses of the state Legislature today.
"Tenders were invited three times between 2002-2009, but were not finalised due to various reasons like non- availability of land parcel from the port trust and internal disputes of the contractors and poor responses of operators," the report said.
Since 2002, the MSRDCL had spent Rs 20.95 crore by appointing consultants to prepare the design for the project and to conduct feasibility study.
Subsequently, in 2014, the government decided not to pursue the western waterways projects and again appointed MMB as the implementing agency for the east coast project in June 2015, the report said.
"The MMB has again floated tenders for appointment of consultants for the project," it added.
The report further stated that the MSRDCL has not been able to conceptualise the project within a span of 10 to 13 years despite being transferred to it.
"The indecision of the government, even after the lapse of 16 years as regards its willingness to go ahead with the project and deciding the implementing agency, the project as envisaged could not be implemented...This has led to a wasteful expenditure of Rs 20.95 crore," it stated.
*Subscribe to Business Standard digital and get complimentary access to The New York Times

Smart Quarterly

₹900

3 Months

₹300/Month

SAVE 25%

Smart Essential

₹2,700

1 Year

₹225/Month

SAVE 46%
*Complimentary New York Times access for the 2nd year will be given after 12 months

Super Saver

₹3,900

2 Years

₹162/Month

Subscribe

Renews automatically, cancel anytime

Here’s what’s included in our digital subscription plans

Exclusive premium stories online

  • Over 30 premium stories daily, handpicked by our editors

Complimentary Access to The New York Times

  • News, Games, Cooking, Audio, Wirecutter & The Athletic

Business Standard Epaper

  • Digital replica of our daily newspaper — with options to read, save, and share

Curated Newsletters

  • Insights on markets, finance, politics, tech, and more delivered to your inbox

Market Analysis & Investment Insights

  • In-depth market analysis & insights with access to The Smart Investor

Archives

  • Repository of articles and publications dating back to 1997

Ad-free Reading

  • Uninterrupted reading experience with no advertisements

Seamless Access Across All Devices

  • Access Business Standard across devices — mobile, tablet, or PC, via web or app

More From This Section

First Published: Aug 05 2016 | 7:42 PM IST

Next Story