Reviewing the work of energy department, Das said underground cabling would be completed in Ranchi, Dhanbad, Jamshedpur, Bokaro and Deoghar by March 2018, an official release said here.
He also asked them to codify transformers so that when necessary it could be identified and action could be initiated.
Das also suggested forest clearance for laying transmission lines in forest areas and appoint any retired forest official as nodal officer.
The chief minister said work would also be carried out under public private partnership to give uninterrupted electricity. There would not be any dearth of funds and if necessary loan from NABARD would be taken, he said.
They said grid sub-station was completed in Dumka, Chaibasa, Madhupur, Mohanpur, Chatra, Simdega and Tamad while work was in progress at Patratu, Latehar, Lohardaga, Gobindpur, Ramchandrapur, Mango and Jainamore (Bokaro), the release said.