Delay in projects completion cost Rlys over Rs 1 lakh cr: CAG

Image
Press Trust of India New Delhi
Last Updated : Dec 18 2015 | 7:07 PM IST
Delay in the execution of more than 400 projects by the Railways resulted in cost overrun of Rs 1.07 lakh crore, the Comptroller and Auditor General of India has said.
The CAG in its latest report which was tabled in Parliament today said "Target dates for completion of projects were either not fixed or not available on records of the Railway Administration. The physical progress was also slow where target for completion of project was fixed."
It further said "Projects were delayed due to delay in preparation/sanction of estimate and delay in acquisition of land. Delay in completion of projects resulted in cost overrun of Rs 1.07 lakh crore and huge throw-forward of Rs 1.86 lakh crore in respect of 442 ongoing projects."
The CAG in its report said there was lack of consistency in prioritisation of projects and also there were several instances of under-utilisation of funds which had adverse impact on the physical progress of projects.
The report observed that while the allotment of funds was not proportionate to the requirement, there were several instances of under-utilisation of funds which had adverse impact on the physical progress of projects.
Noting that during 2009-14, 202 projects were added to the existing shelf of ongoing projects ignoring existing fund constraint and as a result only 67 projects were completed during the same period.
The federal auditor observed that 75 projects are ongoing for more than 15 years and of them, three projects are 30 years old. Despite budgetary support from the Finance Ministry, progress of national projects was far from satisfactory resulting in substantial time and cost overrun.
It has found that the rate of return was less than the prescribed benchmark of 14 per cent in 236 (53 per cent) ongoing projects.
(REOPENS DEL 47)
CAG has found that the progress in respect of cost sharing projects was badly affected as state government declined to bear the enhanced cost of the project and as a result, expenditure to the tune of Rs 13,135 crore incurred on cost sharing projects remained unproductive.
Blaming railways "deficient planning" for collapse of tunnels and bridge diversion, the national auditor said there were several instances of collapse of tunnels, bridges, diversion of alignment, etc resulting in extra/wasteful expenditure in addition to idle investment of Rs 137.41 crore.
"Delay in land acquisition caused slow progress of the project and two projects had to be frozen due to failure in acquisition of land resulting in wasteful expenditure of Rs 60.78 crore," CAG said.
It has suggested that railways need to revisit all projects which are ongoing for more than 15 years and do not fulfil the prescribed Rate of Return for assessing the viability of the projects.
Suggesting the need to ensure optimal utilisation of funds so as to avoid mismatch between allotment and utilisation of fund, CAG recommended that railways ensure timely preparation of estimates with reasonable accuracy for efficient financial control over the project cost.
CAG has also suggested monitoring of execution of projects both at the Railway Board and at the zonal levels which need to be strengthened to avoid wasteful expenditure and blocking up of fund.
*Subscribe to Business Standard digital and get complimentary access to The New York Times

Smart Quarterly

₹900

3 Months

₹300/Month

SAVE 25%

Smart Essential

₹2,700

1 Year

₹225/Month

SAVE 46%
*Complimentary New York Times access for the 2nd year will be given after 12 months

Super Saver

₹3,900

2 Years

₹162/Month

Subscribe

Renews automatically, cancel anytime

Here’s what’s included in our digital subscription plans

Exclusive premium stories online

  • Over 30 premium stories daily, handpicked by our editors

Complimentary Access to The New York Times

  • News, Games, Cooking, Audio, Wirecutter & The Athletic

Business Standard Epaper

  • Digital replica of our daily newspaper — with options to read, save, and share

Curated Newsletters

  • Insights on markets, finance, politics, tech, and more delivered to your inbox

Market Analysis & Investment Insights

  • In-depth market analysis & insights with access to The Smart Investor

Archives

  • Repository of articles and publications dating back to 1997

Ad-free Reading

  • Uninterrupted reading experience with no advertisements

Seamless Access Across All Devices

  • Access Business Standard across devices — mobile, tablet, or PC, via web or app

More From This Section

First Published: Dec 18 2015 | 7:07 PM IST

Next Story