The court asked the Delhi chief secretary to hold a meeting with all stakeholders to take stock of the situation.
"Given the delay in the execution of the work, we are of the view that the execution of work and completion of the bridge deserve scrutiny at the highest level," a bench of Acting Chief Justice Gita Mittal and Justice C Hari Shankar said.
The court's direction came while hearing a public interest litigation (PIL) by advocate Pratibha Chopra, who pointed to the inordinate delay in the project and alleged the construction of the bridge had missed several deadlines since 2011.
According to DTTDC, there was a significant hike in the cost of construction and in an affidavit of November, 2017, it said the cost had been enhanced to Rs 1,575 crore.
The court noted that Rs 1,334.10 crore had already been paid to DTTDC by the Delhi government but the bridge was still nowhere near completion.
It was informed by the DTTDC that subject to the payment of Rs 250 crore, the work would be completed by June this year.
The court had earlier wished to know the variation in costs incurred over the bridge from the time the project was envisaged. It had also sought information from the Delhi government on when the timeline was changed or extended.
The Delhi government's Urban Development department and the Public Works department had earlier informed the court that they had sent to the DCP traffic a request letter for a joint site inspection and working out a diversion plan for vehicular traffic.
Announced in 2004, the project received a nod from the Delhi Cabinet in 2007 and was initially expected to be completed at a modified estimate of Rs 1,131 crore by the Commonwealth Games held here in October, 2010.
The Signature Bridge, when completed, is expected to share the burden of vehicular traffic which is being borne by the Wazirabad bridge.
Seeking to expedite the completion of construction, the plea has contended that lives of lakhs of commuters, who are regularly stranded for over 3-4 hours a day on the Wazirabad bridge, are at a risk as it is an old and ageing bridge which can cave in anytime.
The plea said to avoid any tragic fallout, the agencies should complete the project or else they should be ready to take the responsibility in case of any mishap.
According to the government, the Signature Bridge had obtained environmental clearance in 2011 and was set to be completed by December, 2013. The date of completion was pushed to June, 2016, and then to July, 2017, which was further pushed to December, 2017, and is now expected to be delayed further.
Disclaimer: No Business Standard Journalist was involved in creation of this content
You’ve reached your limit of {{free_limit}} free articles this month.
Subscribe now for unlimited access.
Already subscribed? Log in
Subscribe to read the full story →
Smart Quarterly
₹900
3 Months
₹300/Month
Smart Essential
₹2,700
1 Year
₹225/Month
Super Saver
₹3,900
2 Years
₹162/Month
Renews automatically, cancel anytime
Here’s what’s included in our digital subscription plans
Exclusive premium stories online
Over 30 premium stories daily, handpicked by our editors


Complimentary Access to The New York Times
News, Games, Cooking, Audio, Wirecutter & The Athletic
Business Standard Epaper
Digital replica of our daily newspaper — with options to read, save, and share


Curated Newsletters
Insights on markets, finance, politics, tech, and more delivered to your inbox
Market Analysis & Investment Insights
In-depth market analysis & insights with access to The Smart Investor


Archives
Repository of articles and publications dating back to 1997
Ad-free Reading
Uninterrupted reading experience with no advertisements


Seamless Access Across All Devices
Access Business Standard across devices — mobile, tablet, or PC, via web or app