The Tunnel Boring Machine (TBM) which started the process on this line on January 9 completed the tunnelling of the 1448.40 m-long Azadpur to Shalimar Bagh stretch today with a breakthrough at Shalimar Bagh construction site, according to DMRC Executive Director(Corporate Communications) Anuj Dayal.
The tunnel is at 18 m depth at Azadpur and 16m at Shalimar Bagh.
"Six cross-passages have been made on this stretch at a depth of 30 m and tunnelling for the other tunnel of 1443.50 m is also expected to be completed within a fortnight," Dayal said.
"Approximately 80 trains run per day through this main railway line and the metro construction was done without hampering the railway traffic for even a single day," he said.
This section is a part of 59 km-long Majlis Park to Shiv Vihar corridor of Phase III network that consists of about 14 km of underground lines.