Gomti project: Only 60% work from 90% funds, probe ordered

Image
Press Trust of India Lucknow
Last Updated : Apr 01 2017 | 9:07 PM IST
Noting that only 60 per cent work on Gomti river front project was complete while 90 per cent of the funds were exhausted, Uttar Pradesh government today ordered a high-level probe into the former chief minister Akhilesh Yadav's dream initiative.
Chief Minister Yogi Adityanath, who had inspected the project in the state capital on March 27, held a review meeting here and called for the probe to be headed by a retired High Court judge, a government official said.
He asked the chief secretary to constitute a team for inquiry into the project and submit its report within 45 days, the official said, adding the urban development minister Suresh Khanna and irrigation minister Dharampal Singh have been told to continuously monitor the works of the project.
Expressing dissatisfaction that almost 90 per cent of the Rs 1513-crore budget, which is Rs 1435 crore, have been spent but works on the project are only 60 per cent complete, the Chief Minister asked the probe team to look into the reasons behind delay and expenditure on the project.
He also called for reviewing the necessity of the remaining works and asked for doing away with unimportant works and completion of the project at the earliest.
The officials informed the Chief Minister that the revised estimate of the project has now come to Rs 2448 crore.
The Chief Minister said that before opening the project for public the biggest problem of pollution of the river should have been addressed and asked the officials to divert the drains falling in the river and setting up STP.
"Till the pollution is not addressed, there is no relevance of beautification of the banks," the Chief Minister stressed and asked for proper disposal of the discharge from factories in Lakhimpur and Pilibhit which fall in the river.
During his inspection, the Chief Minister had expressed dissatisfaction over the progress and utility of the project on the banks of the river which was carried out by the irrigation department of the state headed by cabinet minister Akhilesh's uncle Shivpal Singh Yadav.
The Chief Minister also asked the officials to link this project with the 'Namami Gange' project and initiate work for plugging drains falling in the river so that it could be clean and water flow maintained.

Disclaimer: No Business Standard Journalist was involved in creation of this content

*Subscribe to Business Standard digital and get complimentary access to The New York Times

Smart Quarterly

₹900

3 Months

₹300/Month

SAVE 25%

Smart Essential

₹2,700

1 Year

₹225/Month

SAVE 46%
*Complimentary New York Times access for the 2nd year will be given after 12 months

Super Saver

₹3,900

2 Years

₹162/Month

Subscribe

Renews automatically, cancel anytime

Here’s what’s included in our digital subscription plans

Exclusive premium stories online

  • Over 30 premium stories daily, handpicked by our editors

Complimentary Access to The New York Times

  • News, Games, Cooking, Audio, Wirecutter & The Athletic

Business Standard Epaper

  • Digital replica of our daily newspaper — with options to read, save, and share

Curated Newsletters

  • Insights on markets, finance, politics, tech, and more delivered to your inbox

Market Analysis & Investment Insights

  • In-depth market analysis & insights with access to The Smart Investor

Archives

  • Repository of articles and publications dating back to 1997

Ad-free Reading

  • Uninterrupted reading experience with no advertisements

Seamless Access Across All Devices

  • Access Business Standard across devices — mobile, tablet, or PC, via web or app

More From This Section

First Published: Apr 01 2017 | 9:07 PM IST

Next Story