The ongoing work of laying a 12.7-km pipeline for supplying Ganga water to Siddhartha Vihar colony of Awas Vikas Parishad will be completed by next September, an official said.
The project manager Shubhendra Chaudhary told PTI that the pipeline will run along the National Highway-24 and would be connected to Ganga canal of Masuri town in district.
The project will cost Rs 123.69 crore, of which 75 per cent would be paid by the NOIDA authority and 25 per cent by Awas Vikas Parishad, the official said.
He said 37.5 cusecs of Ganga water would be supplied to Noida and 12.5 to Siddhartha vihar colony, in addition to present supply of 5 cusec.
A treatment plant would also be constructed in Siddhartha Vihar area, the official said, adding that the Jal Nigam here will monitor the quality and progress of work.
Disclaimer: No Business Standard Journalist was involved in creation of this content
You’ve reached your limit of {{free_limit}} free articles this month.
Subscribe now for unlimited access.
Already subscribed? Log in
Subscribe to read the full story →
Smart Quarterly
₹900
3 Months
₹300/Month
Smart Essential
₹2,700
1 Year
₹225/Month
Super Saver
₹3,900
2 Years
₹162/Month
Renews automatically, cancel anytime
Here’s what’s included in our digital subscription plans
Exclusive premium stories online
Over 30 premium stories daily, handpicked by our editors


Complimentary Access to The New York Times
News, Games, Cooking, Audio, Wirecutter & The Athletic
Business Standard Epaper
Digital replica of our daily newspaper — with options to read, save, and share


Curated Newsletters
Insights on markets, finance, politics, tech, and more delivered to your inbox
Market Analysis & Investment Insights
In-depth market analysis & insights with access to The Smart Investor


Archives
Repository of articles and publications dating back to 1997
Ad-free Reading
Uninterrupted reading experience with no advertisements


Seamless Access Across All Devices
Access Business Standard across devices — mobile, tablet, or PC, via web or app