Town planning authority MMRDA Friday said the second phase of the much-delayed Jacob Circle-Wadala-Chembur monorail project is likely to commence operations from March 1.
The Mumbai Metropolitan Region Development Authority (MMRDA), which is implementing the 19.5 km long corridor, has received spare parts required to repair the rakes that were gutted in a fire accident in 2017.
"The much awaited monorail parts worth over Rs 3 crore have arrived in the city from Malaysia which will now help MMRDA begin the phase-2 of the project. We are hopeful to commence operations on the Jacob Circle-Wadala corridor from March 1 this year," MMRDA Joint Project Director Dilip Kawathkar said in a statement issued here.
He said the parts will enable MMRDA refurbish four more mono trains into the service of Mumbaikars.
"This means the entire monorail corridor will operate with seven trains. Once commissioned, the entire route will attract many more commuters," Kawathkar added.
The MMRDA has also decided to increase the fares to Rs 10 to Rs 40 for the entire corridor from the current Rs 5 to Rs 11 for the first phase.
MMRDA took over the operations and maintenance of the monorail from Scomi Engineering in the month of December 2018, after it failed to supply the contracted rakes and other operational materials, including the signalling equipment and maintaining the quality of monorail services despite many extensions.
On December 14, town planning authority MMRDA had terminated its contract with the LTSE consortium, which had the contract to build the country's first and only monorail in the megapolis.
Last year one rake went up in flames, while on service, and it forced shutting of the services for many months.
The L&T-Scomi consortium won the Rs 2,460-crore contract in 2009 to build and operate the 19.5-km monorail network on the Chembur-Wadala-Jacob Circle corridor connecting the eastern periphery of the island city to the central parts.
The 8.9-km-long first phase of the monorail from Chembur to Wadala was opened to the public in February 2014, almost four years after the original deadline.
Disclaimer: No Business Standard Journalist was involved in creation of this content
You’ve reached your limit of {{free_limit}} free articles this month.
Subscribe now for unlimited access.
Already subscribed? Log in
Subscribe to read the full story →
Smart Quarterly
₹900
3 Months
₹300/Month
Smart Essential
₹2,700
1 Year
₹225/Month
Super Saver
₹3,900
2 Years
₹162/Month
Renews automatically, cancel anytime
Here’s what’s included in our digital subscription plans
Exclusive premium stories online
Over 30 premium stories daily, handpicked by our editors


Complimentary Access to The New York Times
News, Games, Cooking, Audio, Wirecutter & The Athletic
Business Standard Epaper
Digital replica of our daily newspaper — with options to read, save, and share


Curated Newsletters
Insights on markets, finance, politics, tech, and more delivered to your inbox
Market Analysis & Investment Insights
In-depth market analysis & insights with access to The Smart Investor


Archives
Repository of articles and publications dating back to 1997
Ad-free Reading
Uninterrupted reading experience with no advertisements


Seamless Access Across All Devices
Access Business Standard across devices — mobile, tablet, or PC, via web or app