Lanco says it got favourable APTEL ruling in Amarkantak issue

As per the APTEL order, Amarkantak unit 2 shall be paid regulated tariff based on the actual capital cost of the project

Katya Naidu Mumbai
Last Updated : Jan 03 2014 | 8:24 PM IST
Lanco Infratech's received a favourable verdict on its year-long dispute with Haryana Power Generation Corporation (HPGCL) over the second unit of its Amarkantak power plant.

“As per the Appellate Tribunal for Electricity’ (APTEL) order, Amarkantak Unit 2 shall be paid regulated tariff based on the actual capital cost of the project. This would result in sustainable and profitable operation of the project at full capacity,” said Lanco, in a press release today. The exact tariff for the power plant, is yet to be known as the order has not been made public.

The 300 megawatt second unit which was commissioned, could not start generating due to the dispute, can now start generation. The power generator's power purchase agreement with Power Trading Corporation (PTC) to supply to HPGCL, was terminated. This was over the non-compliance of certain PPA covenants.

The receivables from this unit have been pegged at Rs 195 crore, by the end of the second quarter. The first unit of coal-based Amarkantak power, which is located in Chhattisgarh, has been generating power and earning revenues, unlike the second unit.  

Lanco's Rs 7,700 crore debt recast was approved by its lenders, last month. Amongst other developments, Lanco said that it has two cases pending verdicts with APTEL and that they were expecting favourable judgments.

“Once tariff orders are passed, we will take around six months for payments to be cleared. We expect the payments to come over time and not immediately,” said Adi Babu, the chief financial officer of Lanco, told Business Standard in an interview after its debt recast was approved.

The release of payments from its power plants is one of the positive developments that the company had expected after its corporate debt restructuring (CDR) package was approved by the lenders. As its payments from Karnataka state utility as well as that of Haryana is cleared, the company expects its business to start turnaround by March.
*Subscribe to Business Standard digital and get complimentary access to The New York Times

Smart Quarterly

₹900

3 Months

₹300/Month

SAVE 25%

Smart Essential

₹2,700

1 Year

₹225/Month

SAVE 46%
*Complimentary New York Times access for the 2nd year will be given after 12 months

Super Saver

₹3,900

2 Years

₹162/Month

Subscribe

Renews automatically, cancel anytime

Here’s what’s included in our digital subscription plans

Exclusive premium stories online

  • Over 30 premium stories daily, handpicked by our editors

Complimentary Access to The New York Times

  • News, Games, Cooking, Audio, Wirecutter & The Athletic

Business Standard Epaper

  • Digital replica of our daily newspaper — with options to read, save, and share

Curated Newsletters

  • Insights on markets, finance, politics, tech, and more delivered to your inbox

Market Analysis & Investment Insights

  • In-depth market analysis & insights with access to The Smart Investor

Archives

  • Repository of articles and publications dating back to 1997

Ad-free Reading

  • Uninterrupted reading experience with no advertisements

Seamless Access Across All Devices

  • Access Business Standard across devices — mobile, tablet, or PC, via web or app

More From This Section

First Published: Jan 03 2014 | 7:58 PM IST

Next Story