Officials in South Delhi Municipal Corporation said work is going behind schedule in at least eight such parking projects following the failure of respective agencies to facilitate their implementation.
In case of parking at Subhash Nagar Block 6, there has been a physical progress of a mere 6 per cent when the date of completion as per contract agreement was in February, 2013. Now, the date has been pushed to March, 2014 with SDMC explaining that DJB is shifting its line and hence the work is held up.
At Bhogal and Subhash Nagar Block 10, parking work has been done only to the tune of 40 per cent and 56 per cent respectively. These are now expected to be completed in September 2013 and March 2014 respectively now.
You’ve reached your limit of {{free_limit}} free articles this month.
Subscribe now for unlimited access.
Already subscribed? Log in
Subscribe to read the full story →
Smart Quarterly
₹900
3 Months
₹300/Month
Smart Essential
₹2,700
1 Year
₹225/Month
Super Saver
₹3,900
2 Years
₹162/Month
Renews automatically, cancel anytime
Here’s what’s included in our digital subscription plans
Exclusive premium stories online
Over 30 premium stories daily, handpicked by our editors


Complimentary Access to The New York Times
News, Games, Cooking, Audio, Wirecutter & The Athletic
Business Standard Epaper
Digital replica of our daily newspaper — with options to read, save, and share


Curated Newsletters
Insights on markets, finance, politics, tech, and more delivered to your inbox
Market Analysis & Investment Insights
In-depth market analysis & insights with access to The Smart Investor


Archives
Repository of articles and publications dating back to 1997
Ad-free Reading
Uninterrupted reading experience with no advertisements


Seamless Access Across All Devices
Access Business Standard across devices — mobile, tablet, or PC, via web or app