The auditor's report, for the financial year ending on March 31, 2016, on the performance audit in Re-structured Accelerated Power Development and Reforms Programme (R-APDRP) was tabled in the UP Assembly today.
According to the CAG report, "There was slow progress in implementation of scheme as against the sanctioned cost of Rs 7,971.48 crore of the scheme, expenditure of Rs 3,764. 72 crore was incurred by the DISCOMs (power distribution companies)."
"Due to not completing the projects within the stipulated period, chances of conversion of the loan of Rs 4,110.70 received under the scheme into a grant of Rs 2,332.58 crore looks remote," the report said.