NTPC's Darlipali project to start generating power by March

Image
Press Trust of India Bhubaneswar
Last Updated : Jan 29 2019 | 9:35 PM IST

The National Thermal Power Corporation (NTPC) Tuesday said the first unit of its 1600 MW Darlipali Super Thermal Power Project (DSTPP) in Sundargarh district of Odisha is likely to generate power by the end of March.

"Work on the two units of the project with 800 MW capacity each is progressing simultaneously. Commissioning activity for the first unit is on and it is set to start producing power by end of March," NTPC's Regional Executive Director (East-II), M P Sinha told reporters here.

Stating that the turbine of the Darlipalli power plant is ready, Sinha said the boiler is likely to be completely fit for operations early next month.

Internal cleaning of boiler is in progress at present as it is necessary before start.

While the total cost of the ambitious project is to the tune of Rs 12,000 crore, an amount of Rs 8,500 crore has already been spent so far, he said adding that Odisha will get 50 per cent of the total power produced by the plant.

The second 800 MW unit of the plant is under construction and start generating power around six months after the first unit kicks off generation, Sinha said adding the power plant is expected to become fully operational by September, this year.

The Maharatna company has already concluded power purchase agreements (PPA) with states for the DSTPP.

Coal for Darlipalli power plant would be taken from NTPC's Dulanga coal mine and in case of inadequacy, it would be sourced from Mahanadi Coalfields Ltd (MCL).

Considered the country's largest power producing company, the NTPC at present generates 3,470 MW of power from Talcher Super Thermal Power Station, Talcher Thermal Power Station and solar power station at Kaniha in Angul district.

Its total power generation in Odisha will reach 4270 MW with the start of generation from Unit-1 of Darlipalli project, a company official said.

Disclaimer: No Business Standard Journalist was involved in creation of this content

*Subscribe to Business Standard digital and get complimentary access to The New York Times

Smart Quarterly

₹900

3 Months

₹300/Month

SAVE 25%

Smart Essential

₹2,700

1 Year

₹225/Month

SAVE 46%
*Complimentary New York Times access for the 2nd year will be given after 12 months

Super Saver

₹3,900

2 Years

₹162/Month

Subscribe

Renews automatically, cancel anytime

Here’s what’s included in our digital subscription plans

Exclusive premium stories online

  • Over 30 premium stories daily, handpicked by our editors

Complimentary Access to The New York Times

  • News, Games, Cooking, Audio, Wirecutter & The Athletic

Business Standard Epaper

  • Digital replica of our daily newspaper — with options to read, save, and share

Curated Newsletters

  • Insights on markets, finance, politics, tech, and more delivered to your inbox

Market Analysis & Investment Insights

  • In-depth market analysis & insights with access to The Smart Investor

Archives

  • Repository of articles and publications dating back to 1997

Ad-free Reading

  • Uninterrupted reading experience with no advertisements

Seamless Access Across All Devices

  • Access Business Standard across devices — mobile, tablet, or PC, via web or app

More From This Section

First Published: Jan 29 2019 | 9:35 PM IST

Next Story