Revival of electricity distribution companies or discoms holds the key to bring back the power sector back on track and to ensure optimum utilisation of the installed capacities of electricity generators particularly thermal projects.
"Focus on renewables is undeniably a welcome move by the government. But for making such initiatives work, we have to resolve very fundamental problems of making discoms profitable by reducing commercial losses and rationalising tariffs with all seriousness," Indian Energy Exchange Director (Business Development) Rajesh K Mediratta said.
According to the Power Ministry data, the overall plant load factor (or the proportion of capacity utilisation) was 66.31 per cent this fiscal till November.
The PLF is low because discoms are not able to buy power and generators are running their plants at lower PLF because power cannot be stored.
"The cumulative loss of discoms has impacted the offtake of power, both in the merchant market and also through long- term PPAs. Discoms are reluctant to purchase additional power due to their poor financial health, and consequently there are very few Case I bids coming up," Lanco Infratech Executive Chairman L Madhusudhan Rao said.
Elaborating further, Mediratta said, "For making renewables grow, we will also have to solve problem of its integration in the grid and evolve right framework to handle its intermittency. Government should incentivise all types of power resources to sell through competitive markets rather than forcing them to sell under 25-year long-term PPAs."
Last month, the government launched Ujwal Discom Assurance Yojna or UDAY to ease the financial crunch faced by power distribution companies.
The scheme will effectively help reducing discoms' debts only after the states, discoms and the Centre ink MoUs for availing benefits under the programme as it is optional.
Government is expecting that by March 2016, the states would issue bonds worth Rs 70,000-1,00,000 crore to write off the discoms debts.
The scheme was launched to tackle debt of Rs 4.3 lakh crore on discoms along with other measures to cut power thefts and align consumer tariff with cost of generating electricity.
The states having supported the scheme so far include Andhra Pradesh, Madhya Pradesh, Jharkhand, Rajasthan, Gujarat,
Another major issue before the government is putting in
place a power transmission network to support the huge clean energy capacities and for running existing generation capacity to avoid any congestion.
Government is in the process of auctioning transmission projects worth Rs one lakh crore during this fiscal. It has already auctioned many such projects and improved participation of private players. But experts feel that there is a long way to go.
"The main problem in transmission is obtaining statutory clearances and ROW (Right of Way) related problems. Government should ensure UMPP (Ultra Mega Power Projects) model in transmission also wherein all the statutory clearances and ROW approvals need to be provided to the developer and then he can set up the project as the Government is best capable to obtain these approvals for the project," he added.
Maroo said that the new power tariff policy is aimed at creating more competition, increasing the options available to consumers which would lead to reduction of tariffs for end consumers, improvement in service quality.
The new tariff policy is expected to be approved by the government in next month and is aimed at boosting clean energy and improving regulatory mechanism of discoms for ensuring rollout of big investments in the sector.
Maroo said, "There are some concerns which still linger. Renewable obligation should not be made mandatory for developers because its altogether a different technology and expertise and is being tackled as a separate mandate by Ministry of New and Renewable Energy."
Secondly, renewable tariffs have come down significantly and they are in itself becoming viable so no need to push with this scheme, he added.
Despite all these issues, the government feels that the huge capacity addition coupled with higher generation and improve transmission capacity has resulted in considerably reducing the electricity shortage.
The government is also working on auction of four UMPPs by March 2016. These UMPPs are proposed in Cheyyur (in Tamil Nadu) and Bedabahal (in Odisha), Banka in Bihar and one in Jharkhand.
Also, Rs 32,612 crore Integrated Power Development Scheme has been launched for strengthening sub-transmission and distribution systems this year.
Plan is afoot to reduce transmission losses by 5 per cent, which is significant and it stood at around 27 per cent. A five per cent saving in transmission losses meant that India has additional 15,000 MW of power without any fresh investment, the Power Ministry has said.
You’ve reached your limit of {{free_limit}} free articles this month.
Subscribe now for unlimited access.
Already subscribed? Log in
Subscribe to read the full story →
Smart Quarterly
₹900
3 Months
₹300/Month
Smart Essential
₹2,700
1 Year
₹225/Month
Super Saver
₹3,900
2 Years
₹162/Month
Renews automatically, cancel anytime
Here’s what’s included in our digital subscription plans
Exclusive premium stories online
Over 30 premium stories daily, handpicked by our editors


Complimentary Access to The New York Times
News, Games, Cooking, Audio, Wirecutter & The Athletic
Business Standard Epaper
Digital replica of our daily newspaper — with options to read, save, and share


Curated Newsletters
Insights on markets, finance, politics, tech, and more delivered to your inbox
Market Analysis & Investment Insights
In-depth market analysis & insights with access to The Smart Investor


Archives
Repository of articles and publications dating back to 1997
Ad-free Reading
Uninterrupted reading experience with no advertisements


Seamless Access Across All Devices
Access Business Standard across devices — mobile, tablet, or PC, via web or app
