Safety norms violation led to NTPC Unchahar tragedy: Report

Image
Press Trust of India New Delhi
Last Updated : Dec 10 2017 | 6:50 PM IST
The "violation of safety norms" and the "tearing hurry" shown in commissioning a power unit were key reasons behind the 1 November blast at state-run NTPC's Unchahar power plant in Raebareli, says a report.
The report published by the Delhi Solidarity Group -- a civil society group -- also said that the number of deaths is under reported and migrant labourers with no formal training and safety gears are forced to carry out critical operations of the project.
"Many migrant workers are still missing and their whereabouts are not known to anyone," claims the report titled "How Many Deaths Will It Take... A Preliminary Report on Unchahar Tragedy".
Meanwhile, an email query sent to NTPC on this report remained unanswered.
The 1,550 MW Feroze Gandhi Unchahar Thermal Power project, a coal-based power plant, met with an accident at its Unit VI, which was under construction, killing at least 46 and injuring many, it said.
The report further said that most of the labourers had suffered burns of 50-70 per cent and doctors are of the opinion that even if they recover from injury, they would be impaired for life and the ones with very severe burns might not live more than three to four months.
The report also recommended a judicial enquiry into the accident to investigate it thoroughly and to fix responsibility on the ones who erred.
It also recommended that the government should immediately constitute a task force to ascertain the whereabouts of the missing persons and the Ministry of Power should carry out an audit of all coal power plants to ascertain the state of workers, adherence to safety measures and preparedness for emergencies.
"The tearing hurry in commissioning the unit VI of the Unchanar Thermal Power project, violating all safety norms, is the key reason for the explosion at the project on November 1," the report said.
The reports of NTPC's internal committee and a panel set up under Electricity Act by Power Ministry are yet to be made public.

Disclaimer: No Business Standard Journalist was involved in creation of this content

*Subscribe to Business Standard digital and get complimentary access to The New York Times

Smart Quarterly

₹900

3 Months

₹300/Month

SAVE 25%

Smart Essential

₹2,700

1 Year

₹225/Month

SAVE 46%
*Complimentary New York Times access for the 2nd year will be given after 12 months

Super Saver

₹3,900

2 Years

₹162/Month

Subscribe

Renews automatically, cancel anytime

Here’s what’s included in our digital subscription plans

Exclusive premium stories online

  • Over 30 premium stories daily, handpicked by our editors

Complimentary Access to The New York Times

  • News, Games, Cooking, Audio, Wirecutter & The Athletic

Business Standard Epaper

  • Digital replica of our daily newspaper — with options to read, save, and share

Curated Newsletters

  • Insights on markets, finance, politics, tech, and more delivered to your inbox

Market Analysis & Investment Insights

  • In-depth market analysis & insights with access to The Smart Investor

Archives

  • Repository of articles and publications dating back to 1997

Ad-free Reading

  • Uninterrupted reading experience with no advertisements

Seamless Access Across All Devices

  • Access Business Standard across devices — mobile, tablet, or PC, via web or app

More From This Section

First Published: Dec 10 2017 | 6:50 PM IST

Next Story