This includes profile tests for the basic systems and equipment of the unit, with the unit operating at different levels of electric capacity.
The 1000MW unit is the first reactor at the Kudankulam Nuclear Power Plant Project (KKNPP), which is being built by the NPCIL with Rosatom, Russia's State Energy Corporation. The second unit (reactor) should reach the criticality stage in six months, sources said.
The tests are conducted at different stages when the plant starts generating 50 per cent of the capacity, followed by 75 per cent and then subsequently 100 per cent.
The tests also include disabling of the basic systems of the unit and testing its stability in this situation.
Uvarov added "the next stage follows which is the integrated testing of the power unit. At this stage, the unit is supposed to have worked without interruption for 72 hours, at the capacity of 100 per cent.
You’ve reached your limit of {{free_limit}} free articles this month.
Subscribe now for unlimited access.
Already subscribed? Log in
Subscribe to read the full story →
Smart Quarterly
₹900
3 Months
₹300/Month
Smart Essential
₹2,700
1 Year
₹225/Month
Super Saver
₹3,900
2 Years
₹162/Month
Renews automatically, cancel anytime
Here’s what’s included in our digital subscription plans
Exclusive premium stories online
Over 30 premium stories daily, handpicked by our editors


Complimentary Access to The New York Times
News, Games, Cooking, Audio, Wirecutter & The Athletic
Business Standard Epaper
Digital replica of our daily newspaper — with options to read, save, and share


Curated Newsletters
Insights on markets, finance, politics, tech, and more delivered to your inbox
Market Analysis & Investment Insights
In-depth market analysis & insights with access to The Smart Investor


Archives
Repository of articles and publications dating back to 1997
Ad-free Reading
Uninterrupted reading experience with no advertisements


Seamless Access Across All Devices
Access Business Standard across devices — mobile, tablet, or PC, via web or app