Tokyo 2020 slashes budget to $17 billion

Image
AFP Tokyo
Last Updated : Dec 22 2016 | 9:57 AM IST
Tokyo Olympics organisers unveiled a smaller budget of up to USD 17 billion after coming under pressure to cut ballooning costs.
The figure, down from last month's pledge to cap expenditure at USD 17.78 billion, follows warnings that the bill for the 2020 Games could soar as high as USD 30 billion.
Organising committee chief executive Toshiro Muto yesterday said the entire Games budget will be between 1.6 trillion and 1.8 trillion yen, which he put at USD 15-16.8 billion.
Under the latest exchange rate, the same yen figure is worth USD 13.6-15.3 billion. This year's Rio Games cost USD 12 billion, while London 2012 came USD 13.7 billion under the exchange rate of the time.
Yeterday's figure, the most complete budget yet for Tokyo 2020, comes after officials scrambled to slash the costs of building some Olympic venues.
It was revealed at talks between the Games' organisers, the International Olympic Committee (IOC) and the Tokyo and national governments, who are meeting regularly to try to cut costs.
"This does give the overall picture," IOC vice-president John Coates said by videolink from Sydney.
"We are pleased with the progress you are continuing to make," he said, adding: "We think that we can work with you to find... More savings."
Tokyo governor Yuriko Koike, who was elected this year vowing to bring down costs, said some 40 billion yen would be saved after a review of the canoeing, volleyball and swimming venues.
Koike said the organising committee and Tokyo and central governments will discuss further specifics early next year, including "cost-sharing".
In the battle to cut costs, she had proposed moving the canoeing 400 kilometres (250 miles) north of Tokyo to Miyagi prefecture, one of the areas hardest hit by Japan's 2011 tsunami disaster.
But the idea faced resistance from the organising committee, which argued that changing sites was impractical and could end up costing more.
Koike gave up the plan last month and announced that canoeing will stay in Tokyo as planned, but with the venue built at a sharply reduced cost.
In the previous four-way meeting last month, Muto said the organising committee's working budget was capped at less than two trillion yen (USD 17.78 billion) and officials are committed to pushing it lower.
But Coates refused to accept the figure and said overall costs would have to come down significantly.

Disclaimer: No Business Standard Journalist was involved in creation of this content

*Subscribe to Business Standard digital and get complimentary access to The New York Times

Smart Quarterly

₹900

3 Months

₹300/Month

SAVE 25%

Smart Essential

₹2,700

1 Year

₹225/Month

SAVE 46%
*Complimentary New York Times access for the 2nd year will be given after 12 months

Super Saver

₹3,900

2 Years

₹162/Month

Subscribe

Renews automatically, cancel anytime

Here’s what’s included in our digital subscription plans

Exclusive premium stories online

  • Over 30 premium stories daily, handpicked by our editors

Complimentary Access to The New York Times

  • News, Games, Cooking, Audio, Wirecutter & The Athletic

Business Standard Epaper

  • Digital replica of our daily newspaper — with options to read, save, and share

Curated Newsletters

  • Insights on markets, finance, politics, tech, and more delivered to your inbox

Market Analysis & Investment Insights

  • In-depth market analysis & insights with access to The Smart Investor

Archives

  • Repository of articles and publications dating back to 1997

Ad-free Reading

  • Uninterrupted reading experience with no advertisements

Seamless Access Across All Devices

  • Access Business Standard across devices — mobile, tablet, or PC, via web or app

More From This Section

First Published: Dec 22 2016 | 9:57 AM IST

Next Story