BHEL is the leading supplier of main plant equipment to NTPC and its joint ventures, with a 72% share in their installed capacity. BHEL’s scope of work in the Muzaffarpur project envisaged design, engineering, manufacture, supply, erection and commissioning of steam turbines, generators and boilers, along with associated auxiliaries and electricals, besides controls & instrumentation (C&I) and electrostatic precipitators (ESPs).
The second 195 MW unit is expected to be commissioned in FY 2015-16. Earlier, in the first week of March, 2015, a 660 MW supercritical thermal unit was commissioned by BHEL at Barh in Bihar.