BHEL commissions first unit of Pulichintala hydro power project

The project, being set up by TSGENCO, is located in Guntur district of Telangana

BS B2B Bureau  |  Hyderabad 

BHEL commissions first unit of Pulichintala hydro power project

Bharat Heavy Electricals Limited (BHEL) has successfully commissioned the first unit of the 4x30 MW (HEP) in Telangana. The greenfield project is being set up by in Guntur district of Telangana on the river Krishna. BHEL’s scope of work in the project includes design, manufacture, supply, supervision of erection, testing and commissioning of electrical & mechanical (E&M) package comprising four sets of 30 MW vertical Kaplan turbine & generator along with associated auxiliaries.

The equipment has been manufactured at BHEL’s plants at Bhopal, Jhansi, Rudrapur & Bengaluru.

has commissioned 983 MW of hydro power projects in Telangana, so far. Some of the large hydro projects commissioned by in Telangana are the 500 MW Nagarjuna Sagar PSS and the 300 MW Srisailam Left Bank Power House.

In addition to hydro power generation projects, has commissioned Lift Irrigation Scheme projects of various ratings comprising 21 pump-motor sets totalling to 401 MW in Telangana. is also presently executing 26 pump-motor sets totalling to 2,713 MW for various Lift Irrigation Schemes in Telangana, including Kalwakurthy Stage-III LIS and Pranhita Chevella LIS Package - 6, 8, 10 & 11.

RECOMMENDED FOR YOU

BHEL commissions first unit of Pulichintala hydro power project

The project, being set up by TSGENCO, is located in Guntur district of Telangana

The project, being set up by TSGENCO, is located in Guntur district of Telangana
Bharat Heavy Electricals Limited (BHEL) has successfully commissioned the first unit of the 4x30 MW (HEP) in Telangana. The greenfield project is being set up by in Guntur district of Telangana on the river Krishna. BHEL’s scope of work in the project includes design, manufacture, supply, supervision of erection, testing and commissioning of electrical & mechanical (E&M) package comprising four sets of 30 MW vertical Kaplan turbine & generator along with associated auxiliaries.

The equipment has been manufactured at BHEL’s plants at Bhopal, Jhansi, Rudrapur & Bengaluru.

has commissioned 983 MW of hydro power projects in Telangana, so far. Some of the large hydro projects commissioned by in Telangana are the 500 MW Nagarjuna Sagar PSS and the 300 MW Srisailam Left Bank Power House.

In addition to hydro power generation projects, has commissioned Lift Irrigation Scheme projects of various ratings comprising 21 pump-motor sets totalling to 401 MW in Telangana. is also presently executing 26 pump-motor sets totalling to 2,713 MW for various Lift Irrigation Schemes in Telangana, including Kalwakurthy Stage-III LIS and Pranhita Chevella LIS Package - 6, 8, 10 & 11.

image
Business Standard
177 22

BHEL commissions first unit of Pulichintala hydro power project

The project, being set up by TSGENCO, is located in Guntur district of Telangana

Bharat Heavy Electricals Limited (BHEL) has successfully commissioned the first unit of the 4x30 MW (HEP) in Telangana. The greenfield project is being set up by in Guntur district of Telangana on the river Krishna. BHEL’s scope of work in the project includes design, manufacture, supply, supervision of erection, testing and commissioning of electrical & mechanical (E&M) package comprising four sets of 30 MW vertical Kaplan turbine & generator along with associated auxiliaries.

The equipment has been manufactured at BHEL’s plants at Bhopal, Jhansi, Rudrapur & Bengaluru.

has commissioned 983 MW of hydro power projects in Telangana, so far. Some of the large hydro projects commissioned by in Telangana are the 500 MW Nagarjuna Sagar PSS and the 300 MW Srisailam Left Bank Power House.

In addition to hydro power generation projects, has commissioned Lift Irrigation Scheme projects of various ratings comprising 21 pump-motor sets totalling to 401 MW in Telangana. is also presently executing 26 pump-motor sets totalling to 2,713 MW for various Lift Irrigation Schemes in Telangana, including Kalwakurthy Stage-III LIS and Pranhita Chevella LIS Package - 6, 8, 10 & 11.

image
Business Standard
177 22

Upgrade To Premium Services

Welcome User

Business Standard is happy to inform you of the launch of "Business Standard Premium Services"

As a premium subscriber you get an across device unfettered access to a range of services which include:

  • Access Exclusive content - articles, features & opinion pieces
  • Weekly Industry/Genre specific newsletters - Choose multiple industries/genres
  • Access to 17 plus years of content archives
  • Set Stock price alerts for your portfolio and watch list and get them delivered to your e-mail box
  • End of day news alerts on 5 companies (via email)
  • NEW: Get seamless access to WSJ.com at a great price. No additional sign-up required.
 

Premium Services

In Partnership with

 

Dear Guest,

 

Welcome to the premium services of Business Standard brought to you courtesy FIS.
Kindly visit the Manage my subscription page to discover the benefits of this programme.

Enjoy Reading!
Team Business Standard