CAG pulls up SAIL for delay in expansion plans

Says mismanagement led to escalation in project costs, affected capacity

BS Reporter New Delhi
Last Updated : Aug 12 2015 | 2:37 PM IST
The Comptroller and Auditor General (CAG) has pulled up state-run Steel Authority of India (SAIL) for delaying the modernisation and expansion plans (MEP) of its integrated steel plants for more than four years.

“The integrated commissioning of capacity expansion projects in five integrated steel plants has been delayed by over four years, and is now scheduled for completion during 2015,” said the CAG report. 

According to the report, the project planning, tender finalisation, project execution, and monitoring of MEP implementation were not efficient at all stages of the project management cycle. 

Trying to take advantage of the prevailing buoyant steel market conditions in 2006-07, the company implemented the entire MEP to enhance hot metal production from 13.83 million tonne per annum (MTPA) in 2006-07 to 23.46 MTPA, including corresponding upstream and downstream production facilities across all the steel plants. 

However, it compressed the implementation period by two years to 2010 against 2012 as planned in the corporate plan.

According to CAG, the capacity of the equipment suppliers and contractors were limited. As a result, they were overbooked, which lead them to asking higher prices for their equipments leading to variance in cost estimates and awarded price. 

“The prices obtained through tender during 2006-08 were 70-100% higher than the cost estimates,” the CAG noted. Simultaneously, total cost of proposed MEP projects increased from Rs 43,142 crore, as approved by the SAIL board during 2006-07, to Rs 77,691 crore during 2008-09 - an increase of 80%. 

The CAG also pointed that while the SAIL management had the option to stagger the capacity building plan in phases - to allow the prices of equipment and works to calm down - it chose to continue with its earlier decision.

Also, projects to be deferred were selected in an ad hoc manner, resulting in severe capacity mismatch. 

“Deferment of some of the MEP projects created a situation where full production stream of integrated steel making was broken, resulting in capacity mismatch among the projects in upstream and downstream,” the report said. 

There were also severe delays in handing over of site and work front to the contractors. According to CAG, in 14 contracts amounting to Rs 7,472 crore, there was 11 months to 53 months delay in handing over the front/site to the contractors for construction and erection of main plants.

Moreover, oversight of SAIL board of MEP projects was not effective and it failed to contain the delays consequently. 

Meanwhile, CAG has recommended that company may strengthen their project monitoring system at all levels. 

“There should be appropriate monitoring mechanism at the Plant and the Board level that would not only monitor but should have the authority to take corrective action as well as fix responsibility at each stage of delay,” it said.

*Subscribe to Business Standard digital and get complimentary access to The New York Times

Smart Quarterly

₹900

3 Months

₹300/Month

SAVE 25%

Smart Essential

₹2,700

1 Year

₹225/Month

SAVE 46%
*Complimentary New York Times access for the 2nd year will be given after 12 months

Super Saver

₹3,900

2 Years

₹162/Month

Subscribe

Renews automatically, cancel anytime

Here’s what’s included in our digital subscription plans

Exclusive premium stories online

  • Over 30 premium stories daily, handpicked by our editors

Complimentary Access to The New York Times

  • News, Games, Cooking, Audio, Wirecutter & The Athletic

Business Standard Epaper

  • Digital replica of our daily newspaper — with options to read, save, and share

Curated Newsletters

  • Insights on markets, finance, politics, tech, and more delivered to your inbox

Market Analysis & Investment Insights

  • In-depth market analysis & insights with access to The Smart Investor

Archives

  • Repository of articles and publications dating back to 1997

Ad-free Reading

  • Uninterrupted reading experience with no advertisements

Seamless Access Across All Devices

  • Access Business Standard across devices — mobile, tablet, or PC, via web or app

More From This Section

First Published: Aug 12 2015 | 2:31 PM IST

Next Story