IPPs invest Rs 29,308 cr on projects in Odisha

Sterlite Energy is first IPP to have gone on stream having fully commissioned its 2400 Mw plant at Bhurkamunda

Jayajit Dash Bhubaneswar
Last Updated : Feb 12 2014 | 6:59 PM IST
Independent power producers (IPPs) have invested Rs 29308 crore on their proposed coal-based projects in Odisha.

The promoters who have spent substantially on their projects are Sterlite Energy Ltd (Rs 8038 crore), GMR Kamalanga Energy Ltd (Rs 5,848.62 crore), Lanco Babandh Power Ltd (Rs 4214 crore), Monnet Power Company (Rs 3200 crore) and Jindal India Thermal Power Ltd (Rs 2,893 crore) and Ind Barath Energy (Utkal) Ltd (Rs 2150 crore).

The state government has signed memorandum of understanding (MoU) with 29 IPPs with combined generation capacity of 37440 Mw with the state share being 6,141 Mw.

Also Read

Sterlite Energy is the first IPP to have gone on stream having fully commissioned its 2400 Mw plant at Bhurkamunda near Jharsuguda.

GMR Kamalanga has commissioned two 350 Mw units of its 1400 Mw power station at Kamalanga in Dhenkanal district.

Monnet Power which has proposed 1,050 Mw power project at Nisha near Angul, has completed boundary wall construction. Work on 400 KV transmission line is in progress.

Similarly, Ind Barath Energy (Utkal) Ltd has also completed construction on the boundary wall at the site of its 1360 Mw plant at Sahajbahal near Jharsuguda. The power producer has secured coal linkage for 700 Mw.

Recently, the state government signed fresh agreements with the government are Ind-Barath Energy (Utkal) Ltd, NSL Nagapatnam & Infratech Pvt Ltd, Maa Durga Thermal Power Company Ltd, Visaka Thermal Power Ltd and Monnet Power Company Ltd.

Their lapsed MoUs have been extended keeping in view the strides made in implementation of their coal-fired power plants. The new MoUs are valid for a period of two years from the date of agreement. New MoUs were signed after the law department opined that lapsed MoUs cannot be renewed retrospectively.

According to the fresh MoUs, the IPPs cannot dilute their stake holding to below 51% for at least three years from the date of commencement of their operations. Also, any stake sale beyond this lock-in period will need prior permission of the state government.

The IPPs have to comply with the mandatory clause to promote employment among locals. The clause stipulates that industries setting up their projects in the state have to reserve 90% jobs for locals in the unskilled and semi-skilled category, up to 60% in skilled category and 30% for the supervisory and managerial cadre while giving them the option to fill up the post of senior executives from the open market.
*Subscribe to Business Standard digital and get complimentary access to The New York Times

Smart Quarterly

₹900

3 Months

₹300/Month

SAVE 25%

Smart Essential

₹2,700

1 Year

₹225/Month

SAVE 46%
*Complimentary New York Times access for the 2nd year will be given after 12 months

Super Saver

₹3,900

2 Years

₹162/Month

Subscribe

Renews automatically, cancel anytime

Here’s what’s included in our digital subscription plans

Exclusive premium stories online

  • Over 30 premium stories daily, handpicked by our editors

Complimentary Access to The New York Times

  • News, Games, Cooking, Audio, Wirecutter & The Athletic

Business Standard Epaper

  • Digital replica of our daily newspaper — with options to read, save, and share

Curated Newsletters

  • Insights on markets, finance, politics, tech, and more delivered to your inbox

Market Analysis & Investment Insights

  • In-depth market analysis & insights with access to The Smart Investor

Archives

  • Repository of articles and publications dating back to 1997

Ad-free Reading

  • Uninterrupted reading experience with no advertisements

Seamless Access Across All Devices

  • Access Business Standard across devices — mobile, tablet, or PC, via web or app

More From This Section

First Published: Feb 12 2014 | 6:52 PM IST

Next Story