The National Consumer Disputes Redressal Commission (NCDRC) bench headed by Justice J M Malik directed the firm to hand over the apartments to buyers as per a list proposed by DLF for scheduled possession, failing which it will have to pay a penalty of Rs 5,000 per flat per day to the buyers till the project is completed.
The bench noted that the firm had to give the possession of the property within three years including the grace period from the date of letter of allotment till possession was to be given by 2013. After this, it will have to pay interest till the period it has now proposed before the commission, it said.
If the flats are not given till the period now proposed by the firm, it will carry a penalty of Rs 5,000 per day till its possession, it said.
The bench asked the builder to pay Rs 30,000 compensation each to all the 50 complainants for harassment and anguish.
"It was the bounden duty of the Opposite Parties (firm) to put the complainants in possession of the premises in dispute, within 24 months after acceptance of the first installment. It tantamounts to cheating, if one promises one thing and does not do the same thing within time.
"As a matter of fact, after acceptance of the first installment, the Opposite Party should have worked against the clock (in a hurry to get the order finished). Mutual and free consent is a sine qua non (essential ingredient of an agreement). The said agreement smacks of high handedness, despotism, arrogance and arbitrariness," the bench said.
It noted that the homes should have been given by the end of 2012. "Six months is grace period and six months is the time consumed during the stay order, total time being till 2013," it noted.
"We, therefore, grant concession of three years from the date of letter of allotment till the possession is given. The Opposite Parties are directed to pay to each of the allottee/ allottees, interest at the rate of 12 per cent per annum from the expiry of three years from the date of allotment letter, till the possession is given, besides the penalty of Rs 5,000 per day, if there is further delay, as already ordered," it said.
letters in 2013 or 2014, were entitled to this interest only to the extent of their agreement mentioning 24 months.
"We also impose compensation in the sum of Rs 30,000 to each of the allottee/complainant, towards litigation charges, anger, harassment, anguish, mental agony, frustration and sadness," it said.
According to the complaints, the complainants had applied for flats at DLF Valley, Panchkula in 2010, and later entered into a contract with the firm.
The flats were to be given within 24 months from the date of allotment of provisional allotment letters.
However, the flats were not delivered by the firm and the buyers approached the NCDRC this year.
You’ve reached your limit of {{free_limit}} free articles this month.
Subscribe now for unlimited access.
Already subscribed? Log in
Subscribe to read the full story →
Smart Quarterly
₹900
3 Months
₹300/Month
Smart Essential
₹2,700
1 Year
₹225/Month
Super Saver
₹3,900
2 Years
₹162/Month
Renews automatically, cancel anytime
Here’s what’s included in our digital subscription plans
Exclusive premium stories online
Over 30 premium stories daily, handpicked by our editors


Complimentary Access to The New York Times
News, Games, Cooking, Audio, Wirecutter & The Athletic
Business Standard Epaper
Digital replica of our daily newspaper — with options to read, save, and share


Curated Newsletters
Insights on markets, finance, politics, tech, and more delivered to your inbox
Market Analysis & Investment Insights
In-depth market analysis & insights with access to The Smart Investor


Archives
Repository of articles and publications dating back to 1997
Ad-free Reading
Uninterrupted reading experience with no advertisements


Seamless Access Across All Devices
Access Business Standard across devices — mobile, tablet, or PC, via web or app