Tata Power Company (TPC), India's largest private power utility, has commercialised the 250 mega watt (MW) unit 8 of its Trombay Thermal Power Station (TTPS) in Chembur near Mumbai.
The Unit 8 will operate on imported Indonesian coal and will enhance the generation capacity of the Trombay plant to 1600 MW from the current capacity of 1350 MW. The unit attained full load of 250 MW on March 26 and completed 72 hours of full load trial operation, yesterday.
"Tata Power has been in the forefront to supply uninterrupted quality power to the city of Mumbai, and the addition of this unit further reiterates the company’s commitment to enhance power supply to growing needs of the consumers,” said Prasad R. Menon, managing director, Tata Power.
The Rs1066 crore invested project was started a few years ago, as part of TPC's plans to add 5500 mega watt capacity.
For the last 4-5 years, Maharashtra experiences a power shortage of 4500-5000 MW during summer. Mumbai also has a power shortage of 700-800 MW during the summer period of March to May.
Tata Power first synchronized the unit with the grid during mid-January and coal firing commenced during early March and full load attained on March 26. The commissioning of the unit will help in bridging the ever increasing demand and supply of power for the city of Mumbai, said a company release.
Tata Power, which has 124 mega watt of wind power generation capacity, is also adding another 73 MW at an investment of over Rs600 crore. These projects implemented by Enercon are due for commissioning in March-April period, and about 17 MW is in Maharashtra, said sources.
In a separate statement, Tata Power said its strategic electronics division (SED) has bagged Rs 182.46 crore order from Bharat Electronics to manufacture ‘16 Akash Launchers’ for India's defence forces. To launchers have to be delivered in next 33 months. Since 1991, Tata Power SED has been engaged with the Akash Missile program and in 2005, the division delivered the Air Force version of the Akash launcher as their first integrated design-to-manufacturing project, test firing a missile in 18 months from the date of order placement, said the release.
You’ve reached your limit of {{free_limit}} free articles this month.
Subscribe now for unlimited access.
Already subscribed? Log in
Subscribe to read the full story →
Smart Quarterly
₹900
3 Months
₹300/Month
Smart Essential
₹2,700
1 Year
₹225/Month
Super Saver
₹3,900
2 Years
₹162/Month
Renews automatically, cancel anytime
Here’s what’s included in our digital subscription plans
Exclusive premium stories online
Over 30 premium stories daily, handpicked by our editors


Complimentary Access to The New York Times
News, Games, Cooking, Audio, Wirecutter & The Athletic
Business Standard Epaper
Digital replica of our daily newspaper — with options to read, save, and share


Curated Newsletters
Insights on markets, finance, politics, tech, and more delivered to your inbox
Market Analysis & Investment Insights
In-depth market analysis & insights with access to The Smart Investor


Archives
Repository of articles and publications dating back to 1997
Ad-free Reading
Uninterrupted reading experience with no advertisements


Seamless Access Across All Devices
Access Business Standard across devices — mobile, tablet, or PC, via web or app