58% of construction work in DRDO not completed on time between 2014-19: CAG

The national auditor found that 38 scientists of the DRDO were posted in the construction works department without the approval of the Ministry of Defence

Govt recovered less than 9% service tax arrears in FY17: CAG
Press Trust of India New Delhi
2 min read Last Updated : Dec 22 2021 | 8:34 PM IST

Don't want to miss the best from Business Standard?

Around 58 per cent of the total construction work in the Defence Research and Development Organisation was not completed within the original schedule between 2014 and 2019, the Comptroller and Auditor General of India has said in a report.

Moreover, the national auditor found that 38 scientists of the DRDO were posted in the construction works department without the approval of the Ministry of Defence.

The core activity of DRDO is research and development of technologies required for the armed forces and it had a deficiency of 180 scientists in Defence Research and Development Scientists (DRDS) cadre, the auditor's report, which was tabled in Parliament on Tuesday, noted.

"The purpose of having a dedicated Research and Development Construction Establishment (RDCE) for planning and execution of time bound DRDO works was not fully met as 58 per cent of works for the period 2014-2019 could not be completed within the original schedule," the CAG said reported.

Further, the percentage of works completed within the original schedule declined from 47.09 per cent in 2016-17 to 36.53 per cent in 2018-19, it added.

The national auditor found that the DRDO does not have standards for assessing the requirement of guest houses (GH) similar to that of the defence services wherein the construction of officers' mess is based on the authorised strength of officers at a particular unit.

"Audit observed that occupancy in 53 (41.40 per cent) out of 128 GHs under the jurisdiction of DRDO, was less than 20 per cent during the period from 2014-15 to 2018-19," the report noted.

The CAG audit also found that two additional GHs were constructed at a station that already had three GHs having yearly occupancy between 11 to 42 per cent only.

(Only the headline and picture of this report may have been reworked by the Business Standard staff; the rest of the content is auto-generated from a syndicated feed.)

*Subscribe to Business Standard digital and get complimentary access to The New York Times

Smart Quarterly

₹900

3 Months

₹300/Month

SAVE 25%

Smart Essential

₹2,700

1 Year

₹225/Month

SAVE 46%
*Complimentary New York Times access for the 2nd year will be given after 12 months

Super Saver

₹3,900

2 Years

₹162/Month

Subscribe

Renews automatically, cancel anytime

Here’s what’s included in our digital subscription plans

Exclusive premium stories online

  • Over 30 premium stories daily, handpicked by our editors

Complimentary Access to The New York Times

  • News, Games, Cooking, Audio, Wirecutter & The Athletic

Business Standard Epaper

  • Digital replica of our daily newspaper — with options to read, save, and share

Curated Newsletters

  • Insights on markets, finance, politics, tech, and more delivered to your inbox

Market Analysis & Investment Insights

  • In-depth market analysis & insights with access to The Smart Investor

Archives

  • Repository of articles and publications dating back to 1997

Ad-free Reading

  • Uninterrupted reading experience with no advertisements

Seamless Access Across All Devices

  • Access Business Standard across devices — mobile, tablet, or PC, via web or app

More From This Section

Topics :DRDOconstruction firmsCompanies

First Published: Dec 22 2021 | 8:34 PM IST

Next Story