Mumbai-Delhi industrial corridor stuck in limbo

Maharashtra minister pleads for stay on land acquisition

Sanjay Jog Mumbai
Last Updated : Aug 15 2013 | 10:37 PM IST
The implementation of the ambitious Delhi-Mumbai Industrial Corridor (DMIC) is expected to face further delays as  Maharashtra water resources minister and Raigad district guardian minister Sunil Tatkare of the Nationalist Congress Party (NCP) has requested Chief Minister Prithviraj Chavan to immediately stay land acquisition for the project.

“A large parcel of land has already been acquired for various projects in Raigad district. Seventy five thousand acres is needed for the DMIC project. However, land acquisition needs to be stayed especially in view of strong opposition from the locals,” Tatkare told Business Standard.

Tatkare referred to the Centre's decision to scrap the Dighi port development along the DMIC, following protests against the land acquisition. The Dighi port industrial area project, spread over 270 sq km, was to house a number of manufacturing units and residential colonies.

However, Tatkare said he came across media reports on the state government's move to scale down the Dighi port project.

“A lot of confusion prevails among the farmers from Raigad district and therefore, the government should stay the acquisition of 75,000 acres of land for the DMIC project as a whole,” he noted.

Tatkare’s move comes close on the heels of burgeoning protest from opposition Shiv Sena and Peasants & Workers Party and from various non-governmental organisations.

The Delhi-Mumbai Industrial Corridor project passes through Raigad and Maval parliamentary constituencies and Congress and the NCP are expected to exchange seats during the ensuing seat sharing talks.

The timing of Tatkare’s missive is important. On August 9, when Prithviraj Chavan took the review, it was decided to scale down the Dighi port project.

The state-run Maharashtra Industrial Development Corporation, which is the nodal agency for the Delhi-Mumbai Industrial Corridor  project passing through the state, has already communicated to the government that acquisition of 75,000 acres of land looks impractical. Even though the project can be scaled down, it needs contiguous land.

A government official said the government has not yet lost hope but was prepared to negotiate with the villagers and parties opposing the land acquisition and Delhi-Mumbai Industrial Corridor project in general.

However, the official informed that at Shendre near Aurangabad in Marathwada region, 175 hectares of land has already been acquired for the Delhi-Mumbai Industrial Corridor  project.

A total of 2,500 hectares is required for an industrial centre and an exhibition-cum-convention centre.
*Subscribe to Business Standard digital and get complimentary access to The New York Times

Smart Quarterly

₹900

3 Months

₹300/Month

SAVE 25%

Smart Essential

₹2,700

1 Year

₹225/Month

SAVE 46%
*Complimentary New York Times access for the 2nd year will be given after 12 months

Super Saver

₹3,900

2 Years

₹162/Month

Subscribe

Renews automatically, cancel anytime

Here’s what’s included in our digital subscription plans

Exclusive premium stories online

  • Over 30 premium stories daily, handpicked by our editors

Complimentary Access to The New York Times

  • News, Games, Cooking, Audio, Wirecutter & The Athletic

Business Standard Epaper

  • Digital replica of our daily newspaper — with options to read, save, and share

Curated Newsletters

  • Insights on markets, finance, politics, tech, and more delivered to your inbox

Market Analysis & Investment Insights

  • In-depth market analysis & insights with access to The Smart Investor

Archives

  • Repository of articles and publications dating back to 1997

Ad-free Reading

  • Uninterrupted reading experience with no advertisements

Seamless Access Across All Devices

  • Access Business Standard across devices — mobile, tablet, or PC, via web or app

More From This Section

First Published: Aug 15 2013 | 10:09 PM IST

Next Story